3616 W CADMAN DR 90027
Certificate Information: 3616 W CADMAN DR 90027
- Application / Permit
- 20010-20000-03190
- Plan Check / Job No.
- B20VN12084
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 81'5-1/4" X 54'2-3/4" 2-STORY SFD WITH HABITABLE BASEMENT AND ATTACHED TWO CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | RARES BODEA |
| Corrections Issued | 9/26/2020 | RARES BODEA |
| Quality Review Completed | 9/29/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 3/4/2021 | RARES BODEA |
| Applicant returned to address corrections | 3/5/2021 | RARES BODEA |
| Applicant returned to address corrections | 6/14/2021 | RARES BODEA |
| Applicant returned to address corrections | 9/20/2021 | RARES BODEA |
| Plan Check Approved | 11/17/2021 | RARES BODEA |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 1/27/2025 | ENRIQUE MIRELES |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Disturb/Remove Protected Trees | Cleared | 1/7/2021 | STEPHEN DUPREY |
| Distance to fire station | Cleared | 2/4/2021 | JEREMY CARTER |
| Hydrant and Access approval | Cleared | 2/4/2021 | JEREMY CARTER |
| Address approval | Cleared | 2/17/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/18/2021 | WALLIE JONG |
| Permit | Cleared | 2/18/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/22/2021 | WALLIE JONG |
| Watercourse | Cleared | 2/25/2021 | ALBERT TAM |
| GPI Written Notices | Cleared | 3/9/2021 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 3/9/2021 | RARES BODEA |
| Low Impact Development | Cleared | 8/28/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 9/28/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 11/3/2021 | ADALBERTO VERA |
Contact Information
| Contractor | Trade Construction Services Inc; Lic. No.: 1062967-B | 18717 PARTHENIA STREET #10 NORTHRIDGE, CA 91324 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2021 | Not Ready for Inspection | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/3/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/19/2022 | Partial Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 5/27/2022 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/1/2022 | Conditional Approval | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/10/2022 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 7/1/2022 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 7/5/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/8/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 7/14/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 8/15/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/19/2022 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 8/19/2022 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Partial Approval | JULIAN AMAYA |
| Footing/Foundation/Slab | 10/27/2022 | Conditional Approval | JULIAN AMAYA |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/5/2022 | Partial Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/5/2022 | Approved | MICHAEL LEWIS |
| Deputy Reinf. Concrete | 12/6/2022 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 12/6/2022 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 1/24/2023 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/24/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/9/2023 | Partial Approval | JEFFREY MEAD |
| HVAC-Rough | 2/13/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/23/2023 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 3/23/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/23/2023 | Approved | JOSEPH MCGARRY |
| MERV13>=Rough | 3/23/2023 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 3/23/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 4/27/2023 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 5/17/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/23/2023 | Approved | JOSEPH MCGARRY |
| Shower Pan | 5/23/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/14/2023 | Approved | JOSEPH MCGARRY |
| Sewer | 10/2/2023 | Approved | JOSH MEISTER |
| Service/Power Release | 11/2/2023 | Approved | JOSEPH MCGARRY |
| Gas Test | 6/3/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 6/3/2024 | Approved | ENRIQUE MIRELES |
| Verify Rec and Parks Fee Memo | 6/3/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/25/2024 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 7/25/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 7/25/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/16/2025 | Approved | OSVALDO PARAMO |
| Final | 1/16/2025 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 1/16/2025 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 1/16/2025 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/16/2025 | Approved | OSVALDO PARAMO |
| Final | 1/23/2025 | OK to Issue CofO | ENRIQUE MIRELES |