12136 W VANOWEN ST 1-9 91605

Certificate Information: 12136 W VANOWEN ST 1-9 91605

Application / Permit
20010-20000-03185
Plan Check / Job No.
B20VN12081
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 92' X 48'3" THREE STORY 9 UNIT APARTMENT FULLY SPRINKLERED NFPA-13 (TYPE VA CONSTRUCTION ) WITH BASEMENT GARAGE (TYPE IA ), AFFORDABLE HOUSING INCLUDING 1 LOW INCOME AND 1 VERY LOW INCOME UNIT PER LAMC 12.22A25(C) , ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 1/3/2022
Issuing Office
Current Status
CofO Issued on 9/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Disabled Access Plans Picked Up 9/28/2020 APPLICANT
Green Plans Picked Up 9/28/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 RARES BODEA
Corrections Issued 10/26/2020 RARES BODEA
Quality Review Completed 10/29/2020 STEVEN KIM
Building Plans Picked Up 11/20/2020 APPLICANT
Applicant returned to address corrections 2/5/2021 RARES BODEA
Applicant returned to address corrections 3/22/2021 RARES BODEA
Applicant returned to address corrections 10/13/2021 RARES BODEA
Plan Check Approved 11/4/2021 RARES BODEA
Issued 1/3/2022 APPLICANT
CofO in Progress 8/19/2025 ROBERT DAVIS
Permit Finaled 9/8/2025 RICKEY JACKSON
CofO Issued 9/8/2025 RICKEY JACKSON
Permit Finaled 9/8/2025 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 1/28/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/2/2021 GUILLERMO PETRA
Sewer availability Cleared 2/4/2021 GUILLERMO PETRA
Fire Marshall Fire Life Safety Cleared 4/14/2021 MENOA AGHAJANI
Frnt yard landscape/Water mgmt Cleared 4/15/2021 STEVEN WECHSLER
Opn space landscape/Water mgmt Cleared 4/15/2021 STEVEN WECHSLER
Permit Cleared 4/26/2021 GUILLERMO PETRA
Trees in Parkway Cleared 4/26/2021 JOHN KIM
Redevelopment Project Area Cleared 4/27/2021 DAVID URITA
Highway dedication Cleared 5/4/2021 GUILLERMO PETRA
DAS Clearance Cleared 5/13/2021 NORLITO MEDRANO
Hydrant and Access approval Cleared 5/22/2021 ROBERT DUFF
Excavation more than 5-ft deep Cleared 6/22/2021 CALOSHA APPROVED
Green Code Cleared 7/1/2021 MICHAEL AYERS
Low Impact Development Cleared 7/5/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 7/6/2021 LEE GUILBEAUX
Density Bonus 12.22.A.25 Cleared 9/21/2021 DORIS KWOK
Density Bonus 12.22.A.25 Cleared 9/21/2021 DORIS KWOK

Contact Information

Contractor Owner-Builder       ,
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/13/2022 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/16/2022 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 11/21/2022 Conditional Approval ROBERT DAVIS
Deputy Reinf. Masonry 1/27/2023 Approved JOHN KITCKO
Deputy Drilled-In Anchors 2/6/2023 Conditional Approval JOHN KITCKO
Deputy Drilled-In Anchors 2/7/2023 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/7/2023 Approved JOHN KITCKO
Green Building Rough 2/7/2023 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 2/7/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 2/7/2023 Approved JOHN KITCKO
Green Building Rough 2/16/2023 No Access for Inspection BRIAN KELLY
Masonry Wall/Backfill 2/16/2023 No Access for Inspection BRIAN KELLY
Reinforced Masonry Frame 2/16/2023 No Access for Inspection BRIAN KELLY
Masonry Wall/Backfill 2/17/2023 Partial Inspection JEFFREY FULTON
Deputy Other (see comments) 3/9/2023 Approved JOHN KITCKO
Deputy Other (see comments) 3/22/2023 Conditional Approval JOHN KITCKO
Green Building Rough 3/24/2023 Partial Approval JOHN KITCKO
Piling/Pier/Caisson 3/24/2023 Partial Approval JOHN KITCKO
Reinforced Masonry Frame 3/24/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 3/28/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 4/20/2023 Partial Approval JOHN KITCKO
Deputy Drilled-In Anchors 5/23/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/23/2023 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 5/30/2023 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 5/31/2023 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/1/2023 No Access for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/2/2023 Partial Inspection JOHN KITCKO
Special/Order Compliance 6/2/2023 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 6/6/2023 Corrections Issued JOHN KITCKO
Special/Order Compliance 6/6/2023 Partial Approval STEVEN LEVITT
Excavation/Setback/Form/Re-Bar 6/8/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 6/12/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Corrections Issued JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 7/18/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 7/18/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 8/10/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/15/2023 Partial Approval JOHN KITCKO
Deputy Steel/Welding 8/24/2023 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 8/31/2023 Conditional Approval JEFFREY FULTON
Deputy Wood Construction 9/1/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 11/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/28/2023 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/28/2023 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 12/13/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 12/13/2023 Partial Approval JOHN KITCKO
Insulation 12/20/2023 Partial Approval ROBERT DAVIS
Drywall Nailing 1/2/2024 Partial Approval JOHN KITCKO
Green Building Rough 1/2/2024 Not Ready for Inspection JOHN KITCKO
Verify Rec and Parks Fee Memo 1/2/2024 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 1/5/2024 No Access for Inspection JOHN KITCKO
Drywall Nailing 1/10/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 1/10/2024 Not Ready for Inspection JEFFREY FULTON
Pre-Inspection 1/11/2024 Partial Approval JOHN KITCKO
Drywall Nailing 1/16/2024 Partial Approval JOHN KITCKO
Green Building Rough 1/16/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 1/31/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 1/31/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 1/31/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 2/20/2024 Not Ready for Inspection DEANDRE HOFFMAN
Special/Order Compliance 2/20/2024 Partial Inspection MELVIN GIRTON
Wood Frame 2/20/2024 Partial Inspection DEANDRE HOFFMAN
Insulation 2/23/2024 Partial Approval JOHN KITCKO
Drywall Nailing 2/28/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 2/28/2024 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 3/1/2024 Partial Approval JOHN KITCKO
Green Building Rough 3/1/2024 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 3/20/2024 Partial Approval ROBERT DAVIS
Green Building Rough 3/20/2024 Approved ROBERT DAVIS
Wood Frame 3/26/2024 Partial Approval JOHN KITCKO
Drywall Nailing 3/28/2024 Partial Approval JOHN KITCKO
Drywall Nailing 4/1/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 4/9/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 4/9/2024 Conditional Approval JOHN KITCKO
T-Bar Ceiling 4/9/2024 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 4/25/2024 Partial Approval JOHN KITCKO
Drywall Nailing 5/1/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 7/8/2024 Not Ready for Inspection JOHN KITCKO
T-Bar Ceiling 7/8/2024 Partial Approval JOHN KITCKO
Drywall Nailing 7/16/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 1/7/2025 Partial Inspection JOHN KITCKO
Special/Order Compliance 1/9/2025 Partial Inspection JOHN KITCKO
Drywall Nailing 5/8/2025 Approved JOHN KITCKO
Final 5/8/2025 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 5/8/2025 Approved JOHN KITCKO
Green Building Final 5/8/2025 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 5/8/2025 Approved JOHN KITCKO
Reinforced Masonry Frame 5/8/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 5/8/2025 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 5/8/2025 Approved JOHN KITCKO
Wood Frame 5/8/2025 Approved JOHN KITCKO
Final 8/11/2025 Not Ready for Inspection JOHN KITCKO
Green Building Final 8/11/2025 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved JOHN KITCKO
Smoke Detectors 8/11/2025 Approved JOHN KITCKO
Final 8/18/2025 OK to Issue CofO ROBERT DAVIS