13215 N NORRIS AVE 91342

Certificate Information: 13215 N NORRIS AVE 91342

Application / Permit
20010-20000-03176
Plan Check / Job No.
B20VN12062
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
NEW 16 X 10 STORAGE SHED.
Permit Issued
Issued on 1/11/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 LUIS RINCON
Corrections Issued 9/22/2020 LUIS RINCON
Applicant returned to address corrections 11/4/2020 LUIS RINCON
Plan Check Approved 12/15/2020 LUIS RINCON
Issued 1/11/2021 APPLICANT
CofO in Progress 8/2/2022 ARAM AVEDISIAN
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/19/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/1/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Cahalan,, Timothy Donald; Lic. No.: C80850 14818 FAIRWAY CIRCLE      LEAWOOD, KS 66224

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/8/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/16/2021 Approved MISAEL ESPARZA
Green Building Rough 3/22/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 3/22/2021 Approved MISAEL ESPARZA
Wood Frame 3/22/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/30/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/30/2021 Approved MISAEL ESPARZA
Wood Frame 3/30/2021 Approved MISAEL ESPARZA
Drywall Nailing 4/22/2021 Approved MISAEL ESPARZA
Final 4/22/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 4/22/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/22/2021 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 4/22/2021 Approved MISAEL ESPARZA
Final 5/24/2021 Conditional Approval DANIEL ORRANTE
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Approved DANIEL ORRANTE