13215 N NORRIS AVE 91342
Certificate Information: 13215 N NORRIS AVE 91342
- Application / Permit
- 20010-20000-03176
- Plan Check / Job No.
- B20VN12062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- NEW 16 X 10 STORAGE SHED.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2020 | LUIS RINCON |
| Corrections Issued | 9/22/2020 | LUIS RINCON |
| Applicant returned to address corrections | 11/4/2020 | LUIS RINCON |
| Plan Check Approved | 12/15/2020 | LUIS RINCON |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 8/2/2022 | ARAM AVEDISIAN |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Issued | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cahalan,, Timothy Donald; Lic. No.: C80850 | 14818 FAIRWAY CIRCLE LEAWOOD, KS 66224 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2021 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/16/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/22/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/22/2021 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/22/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/30/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/30/2021 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/30/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 4/22/2021 | Approved | MISAEL ESPARZA |
| Final | 4/22/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 4/22/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 4/22/2021 | Approved | MISAEL ESPARZA |
| Final | 5/24/2021 | Conditional Approval | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Approved | DANIEL ORRANTE |