15015 W OTSEGO ST 91403
Certificate Information: 15015 W OTSEGO ST 91403
- Application / Permit
- 20010-20000-03173
- Plan Check / Job No.
- B20VN12054
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (58'-0"x 42'-6") 2-STORY SINGLE FAMILY DWELLING W/ATT TWO CAR GARAGE, NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | TROY DEGUZMAN |
| Corrections Issued | 9/19/2020 | TROY DEGUZMAN |
| Quality Review Completed | 9/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Applicant returned to address corrections | 3/12/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 4/1/2021 | TROY DEGUZMAN |
| Plan Check Approved | 4/5/2021 | TROY DEGUZMAN |
| Issued | 4/5/2021 | APPLICANT |
| CofO in Progress | 12/10/2021 | JACK KARGODORIAN |
| CofO Issued | 1/8/2022 | MICHAEL SMITH |
| Permit Finaled | 1/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/26/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/29/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/31/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 3/12/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/16/2021 | Conditional Approval | BEAU COLLINS |
| Reinforced Concrete Frame | 4/19/2021 | Off-Hour Fees Due | |
| Reinforced Masonry Frame | 4/19/2021 | Approved | DANIEL DREW |
| Reinforced Concrete Frame | 4/20/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 4/22/2021 | Approved | CHARLES POWELL |
| Reinforced Concrete Frame | 4/22/2021 | Approved | CHARLES POWELL |
| Wood Frame | 5/6/2021 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Rough | 6/14/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 6/14/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 6/15/2021 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 6/15/2021 | Approved | CHARLES POWELL |
| Verify Sprinkler Sign Off | 6/15/2021 | Approved | CHARLES POWELL |
| Deputy Wood Construction | 6/16/2021 | Conditional Approval | STEPHANIE SWANSON |
| Insulation | 6/29/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/29/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 7/6/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/23/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 11/23/2021 | Partial Approval | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 11/23/2021 | Approved | MATT KELLERMAN |
| Smoke Detectors | 11/23/2021 | Approved | MATT KELLERMAN |
| Final | 12/10/2021 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 12/10/2021 | Approved | JACK KARGODORIAN |