10516 W ADDISON ST 91601

Certificate Information: 10516 W ADDISON ST 91601

Application / Permit
20010-20000-03156
Plan Check / Job No.
B20VN11961
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ATT. TRELLIS, FULLY SPRINKLERED PER NFPA13D.
Permit Issued
Issued on 7/25/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 MOHAMMAD ESMAILI
Corrections Issued 10/14/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/30/2020 OMID HEDAYAT
Building Plans Picked Up 11/4/2020 APPLICANT
Applicant returned to address corrections 11/17/2021 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/4/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/11/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/18/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 5/25/2022 MOHAMMAD ESMAILI
Plan Check Approved 7/20/2022 MOHAMMAD ESMAILI
Plan Check Approved 7/25/2022 KAREN HYDE
Issued 7/25/2022 APPLICANT
CofO in Progress 4/12/2024 JOHN HAYES
CofO in Progress 4/26/2024 ROBERT GOLD
No Progress 4/26/2024 ROBERT GOLD
Permit Finaled 4/30/2024 RUBEN SALAS
CofO Issued 4/30/2024 RUBEN SALAS
Permit Finaled 4/30/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/16/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/16/2021 LEE GUILBEAUX
Miscellaneous Cleared 6/16/2021 LEE GUILBEAUX
Permit Cleared 6/16/2021 LEE GUILBEAUX
Sewer availability Cleared 6/16/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 10/16/2021 ROBERT DUFF
Construction near power lines Cleared 11/1/2021 TORI CHEN
Low Impact Development Cleared 2/17/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/24/2022 JOHN LIN
Trees in Parkway Cleared 3/30/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/18/2022 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 10/24/2022 Approved JOHN HAYES
Footing/Foundation/Slab 10/24/2022 Partial Approval JOHN HAYES
Deputy Reinf. Concrete 10/27/2022 Conditional Approval JOHN HAYES
Underground Mechanical 11/4/2022 Partial Approval JOHN HAYES
Footing/Foundation/Slab 11/16/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval JOHN HAYES
Deputy Wood Construction 5/16/2023 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 5/22/2023 Partial Approval JOHN HAYES
HVAC-Rough 5/22/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 5/22/2023 Partial Approval JOHN HAYES
Wood Frame 5/22/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 6/12/2023 Conditional Approval JOHN HAYES
ELECTRICAL-Rough 6/12/2023 Approved JOHN HAYES
Green Building Rough 6/12/2023 Approved JOHN HAYES
HVAC-Rough 6/12/2023 Approved JOHN HAYES
PLUMBING-Rough 6/12/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 6/12/2023 Not Ready for Inspection JOHN HAYES
Insulation 6/20/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/20/2023 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/20/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 7/3/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/27/2023 Approved RYAN SALAZAR
Gas Test 10/11/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/5/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/5/2024 Corrections Issued JENNIFER RABUCHIN
Final 4/5/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 4/5/2024 Approved JENNIFER RABUCHIN
HVAC-Final 4/5/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/5/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/5/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 4/5/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 4/5/2024 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 4/5/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/10/2024 Approved JOSE AVILA
Final 4/10/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved JOSE AVILA
Final 4/12/2024 OK to Issue CofO JOHN HAYES
Service/Power Release 4/12/2024 Approved JOHN HAYES