9452 N REVERIE ROAD 91042
Certificate Information: 9452 N REVERIE ROAD 91042
- Application / Permit
- 20010-20000-03141
- Plan Check / Job No.
- B20VN11902
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (29'-6",48'-2"), 1182 SQFT IRR SHAPE 2-STORY SINGLE FAMILY DWELLING WITH ATT. 2-CAR GARAGE (398 SQFT) AND BALCONY, NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Valley
- Current Status
- Issued on 10/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/19/2020 | TROY DEGUZMAN |
| Quality Review Completed | 10/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| Applicant returned to address corrections | 3/22/2023 | PETER MOSESIAN |
| Applicant returned to address corrections | 3/29/2024 | PETER MOSESIAN |
| Plan Check Approved | 10/18/2024 | PETER MOSESIAN |
| Issued | 10/22/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/30/2020 | GUILLERMO PETRA |
| Address approval | Cleared | 5/17/2021 | ADRIAN CASTRO |
| Specific Plan | Cleared | 6/29/2021 | PEGGY MALONE-BROWN |
| ZI | Cleared | 6/29/2021 | PEGGY MALONE-BROWN |
| Trees in Parkway | Cleared | 8/19/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 10/11/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 12/13/2021 | BRIAN MILLER |
| Grading Pre-Inspection | Cleared | 12/13/2021 | BRIAN MILLER |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 8/16/2022 | LEE GUILBEAUX |
| ZA Case | Cleared | 4/10/2023 | STEVEN WECHSLER |
| Private sewage disp. approval | Cleared | 9/18/2023 | DAN RYAN EVANGELISTA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2023 | COLIN LOREDO |
| Permit | Cleared | 10/27/2023 | COLIN LOREDO |
| Miscellaneous | Cleared | 11/21/2023 | RUBEN VASQUEZ |
| Senate Bill 9 | Cleared | 11/21/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 11/21/2023 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 8/16/2024 | MARTIN FRAGOSO |
| BHO/Hillside ordinance | Cleared | 9/25/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/3/2024 | CARLOS RAMIREZ |
| BHO/Hillside ordinance | Cleared | 10/6/2024 | LEE GUILBEAUX |
Contact Information
| Architect | Mizuki,, Steve Massanori; Lic. No.: C22676 | 2155 VERDUGO BLVD # 330 MONTROSE, CA 91020 |
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
| Landscape Architect | Lysne,, Matthew W; Lic. No.: LA4718 | 344 PASQUAL AVE. SAN GABRIEL, CA 91775 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Underground Mechanical | 7/27/2026 |
Inspection Request History
| Pre-Inspection | 11/6/2024 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/9/2025 | Corrections Issued | DAVID ANDERSON |
| Special/Order Compliance | 6/9/2025 | Approved | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/18/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/18/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/25/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 8/13/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/13/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2025 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/21/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2025 | Partial Approval | DAVID ANDERSON |
| PLUMBING-Rough | 12/18/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2026 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2026 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2026 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 4/6/2026 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/16/2026 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/16/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/16/2026 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/16/2026 | Approved | DAVID ANDERSON |
| Insulation | 4/24/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 5/4/2026 | Approved | DAVID ANDERSON |
| Insulation | 5/4/2026 | Approved | DAVID ANDERSON |
| Shower Pan | 5/8/2026 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/26/2026 | Corrections Issued | DAVID MATSON |
| Interior/Exterior Lathing | 5/29/2026 | Approved | DAVID ANDERSON |