16702 W LA MAIDA ST 91436
Certificate Information: 16702 W LA MAIDA ST 91436
- Application / Permit
- 20010-20000-03099
- Plan Check / Job No.
- B20VN11800
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 46'-3" X 7'-1" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGOUT
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | SELLA BENYAMIN |
| Corrections Issued | 10/7/2020 | SELLA BENYAMIN |
| Quality Review Completed | 10/8/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/14/2020 | APPLICANT |
| Plan Check Approved | 2/2/2021 | SELLA BENYAMIN |
| Issued | 2/3/2021 | APPLICANT |
| CofO in Progress | 9/22/2021 | RONALD COWAN |
| Permit Finaled | 10/13/2021 | MICHAEL SMITH |
| CofO Issued | 10/13/2021 | MICHAEL SMITH |
| Permit Finaled | 10/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2020 | LEE GUILBEAUX |
| Permit | Cleared | 11/23/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/23/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/23/2020 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 12/14/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/17/2020 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 1/14/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/28/2021 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 3/2/2021 | Partial Approval | RONALD COWAN |
| Underground Mechanical | 3/2/2021 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 3/4/2021 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 3/10/2021 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 3/12/2021 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 3/18/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/26/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 4/26/2021 | Approved | RONALD COWAN |
| PLUMBING-Rough | 4/26/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 4/30/2021 | Approved | RONALD COWAN |
| Green Building Rough | 4/30/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/30/2021 | Partial Approval | RONALD COWAN |
| Shower Pan | 4/30/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 4/30/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 5/10/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 5/10/2021 | Approved | SEAN WIRCH |
| Special/Order Compliance | 6/30/2021 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 7/23/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| ELECTRICAL-Final | 8/31/2021 | Approved | RONALD COWAN |
| Gas Test | 8/31/2021 | Approved | RONALD COWAN |
| HVAC-Final | 8/31/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 8/31/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 9/14/2021 | Approved | RONALD COWAN |
| Service/Power Release | 9/14/2021 | Approved | RONALD COWAN |
| Final | 9/21/2021 | OK to Issue CofO | RONALD COWAN |
| Green Building Final | 9/21/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | RONALD COWAN |
| Smoke Detectors | 9/21/2021 | Approved | RONALD COWAN |