11336 W ALLEGHENY ST 91352
Certificate Information: 11336 W ALLEGHENY ST 91352
- Application / Permit
- 20010-20000-03084
- Plan Check / Job No.
- B20VN11787
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER WFPP "The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 10/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/20/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 9/21/2020 | APPLICANT |
| Plan Check Approved | 10/4/2022 | MINA HABILI |
| Issued | 10/7/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | DAVID ANDERSON |
| Permit Finaled | 10/15/2023 | RUBEN SALAS |
| CofO Issued | 10/15/2023 | RUBEN SALAS |
| Permit Finaled | 10/15/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | ADRIAN CASTRO |
| Permit | Cleared | 9/24/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/2/2020 | JEREMY CARTER |
| Specific Plan | Cleared | 8/23/2022 | PEGGY MALONE-BROWN |
| ZI | Cleared | 9/1/2022 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 10/4/2022 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 10/4/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2022 | Corrections Issued | DAVID ANDERSON |
| METHANE-Barrier | 10/17/2022 | Not Ready for Inspection | DAVID ANDERSON |
| METHANE-Subgrade | 10/17/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/25/2022 | Approved | DAVID ANDERSON |
| METHANE-Barrier | 10/25/2022 | Approved | DAVID ANDERSON |
| METHANE-Subgrade | 10/25/2022 | Approved | DAVID ANDERSON |
| Gas Test | 10/31/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/31/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 10/31/2022 | Approved | DAVID ANDERSON |
| Gas Test | 11/3/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/3/2022 | Partial Approval | DAVID ANDERSON |
| Sewer | 11/3/2022 | Approved | DAVID ANDERSON |
| Wood Frame | 11/3/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/21/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/21/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 11/23/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/29/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/1/2022 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 12/1/2022 | Approved | WILLIAM WREN |
| Green Building Rough | 12/5/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 12/5/2022 | Approved | DAVID ANDERSON |
| METHANE-Rough | 12/5/2022 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/5/2022 | Approved | DAVID ANDERSON |
| Insulation | 12/20/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/27/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 1/19/2023 | Corrections Issued | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/23/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 1/23/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/15/2023 | Approved | DAVID ANDERSON |
| Final | 5/15/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 5/15/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | DAVID ANDERSON |
| Service/Power Release | 5/15/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 5/15/2023 | Approved | DAVID ANDERSON |
| Final | 5/22/2023 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 5/22/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 6/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 6/2/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 8/16/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 8/16/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 8/24/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 8/24/2023 | Approved | DAVID ANDERSON |