20011 W WELLS DR 91364
Certificate Information: 20011 W WELLS DR 91364
- Application / Permit
- 20010-20000-03066
- Plan Check / Job No.
- B20VN11746
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 89' X 72' IRR.-SHAPE 1-STORY SINGLE FAMILY DWELLING WITH 19' 11" X 21' ATTACHED 2-CAR GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/19/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 9/22/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Plan Check Approved | 2/10/2021 | GURUNATH NESARAJAH |
| Issued | 2/25/2021 | APPLICANT |
| CofO in Progress | 2/16/2022 | DAVID SANDOVAL |
| Permit Finaled | 3/4/2022 | JOHN JANSON |
| CofO Issued | 3/4/2022 | JOHN JANSON |
| Permit Finaled | 3/4/2022 | JOHN JANSON |
Permit Application Clearance Information
| Permit | Cleared | 10/19/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/22/2020 | MARKOS PEREZ-BRAN |
| ZI | Cleared | 11/23/2020 | STEVEN WECHSLER |
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 12/22/2020 | JOHN KIM |
| Low Impact Development | Cleared | 12/30/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 2/3/2021 | GURUNATH NESARAJAH |
| Grading Pre-Inspection | Cleared | 2/3/2021 | GURUNATH NESARAJAH |
| Miscellaneous | Cleared | 2/23/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 3/22/2021 | Corrections Issued | DAVID SANDOVAL |
| Deputy Reinf. Concrete | 3/25/2021 | Conditional Approval | PETER FOLLING |
| Footing/Foundation/Slab | 3/30/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2021 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 4/20/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/22/2021 | Approved | DAVID SANDOVAL |
| Shower Pan | 4/22/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/6/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/13/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/13/2021 | Approved | DAVID SANDOVAL |
| Insulation | 5/13/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/13/2021 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/13/2021 | Approved | DAVID SANDOVAL |
| Wood Frame | 5/13/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 5/21/2021 | Approved | DAVID SANDOVAL |
| Gas Test | 10/8/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| ELECTRICAL-Final | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| Final | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| Green Building Final | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| HVAC-Final | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 12/22/2021 | No Access for Inspection | DAVID SANDOVAL |
| Service/Power Release | 1/24/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 1/27/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 1/27/2022 | Approved | DAVID SANDOVAL |
| Service/Power Release | 1/27/2022 | Approved | DAVID SANDOVAL |
| Final | 2/14/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 2/14/2022 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 2/14/2022 | Approved | DAVID SANDOVAL |
| Final | 2/16/2022 | OK to Issue CofO | DAVID SANDOVAL |