8013 N DE SOTO AVE 91304
Certificate Information: 8013 N DE SOTO AVE 91304
- Application / Permit
- 20010-20000-03065
- Plan Check / Job No.
- B20VN11745
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18' X 20' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 1/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/21/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/21/2020 | APPLICANT |
| Plan Check Approved | 1/5/2021 | SELLA BENYAMIN |
| Issued | 1/19/2021 | APPLICANT |
| CofO in Progress | 1/20/2022 | STEVEN BACK |
| Permit Finaled | 1/26/2022 | JOHN JANSON |
| CofO Issued | 1/26/2022 | JOHN JANSON |
| Permit Finaled | 1/26/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/9/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 11/10/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 12/3/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Dave'S Remodeling Inc; Lic. No.: 962447-B | 17734 LUDLOW ST GRANADA HILLS, CA 91344 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/18/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/3/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 4/16/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 4/16/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 4/16/2021 | Corrections Issued | HENRY KIM |
| Sewer | 4/16/2021 | Approved | HENRY KIM |
| Underground Mechanical | 4/16/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 4/29/2021 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 4/29/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 4/29/2021 | Approved | HENRY KIM |
| Underground Mechanical | 4/29/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/13/2021 | Approved | HENRY KIM |
| Green Building Rough | 5/13/2021 | Approved | HENRY KIM |
| Insulation | 5/13/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/13/2021 | Approved | HENRY KIM |
| Pre-Inspection | 5/13/2021 | Approved | HENRY KIM |
| Drywall Nailing | 5/21/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 10/7/2021 | Corrections Issued | HENRY KIM |
| Final | 10/7/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 10/7/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 10/7/2021 | Approved | HENRY KIM |
| HVAC-Final | 10/7/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 10/7/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 10/7/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 10/7/2021 | Approved | HENRY KIM |
| Final | 12/6/2021 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Approved | STEVEN BACK |
| Final | 1/6/2022 | Corrections Issued | STEVEN BACK |
| Special/Order Compliance | 1/6/2022 | Approved | STEVEN BACK |
| Final | 1/20/2022 | OK to Issue CofO | STEVEN BACK |