1717 N WINONA BLVD 1-15 90027

Certificate Information: 1717 N WINONA BLVD 1-15 90027

Application / Permit
20010-20000-03061
Plan Check / Job No.
B20VN11723
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 138'10" X 48'8" 15 UNITS 5-STORY TYPE V-A APARTMENT BUILDING WITH TYPE I-A FIRST FLOOR GARAGE. FULLY SPRINKLERED, NFPA-13. TOC TIER 3, 3 EXTREMELY LOW INCOME UNITS , ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Disabled Access Plans Picked Up 9/25/2020 APPLICANT
Green Plans Picked Up 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 RODNEY SAMIIAN
Corrections Issued 10/8/2020 RODNEY SAMIIAN
Quality Review Completed 10/13/2020 CHON CHIO KUO
Building Plans Picked Up 10/15/2020 APPLICANT
Applicant returned to address corrections 6/21/2021 RARES BODEA
Applicant returned to address corrections 5/13/2022 RARES BODEA
Plan Check Approved 2/7/2023 RARES BODEA
Issued 2/8/2023 APPLICANT
CofO in Progress 1/27/2026 DAVID BURKHEAD
Permit Finaled 1/27/2026 ERNESTO CORRAL
CofO Issued 1/27/2026 ERNESTO CORRAL
Permit Finaled 1/27/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 10/16/2020 ELAINE LEI
Highway dedication Cleared 10/16/2020 ELAINE LEI
Permit Cleared 10/16/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 11/24/2020 ELAINE LEI
Hydrant and Access approval Cleared 12/16/2020 MATTHEW CRAIG
Sewer availability Cleared 2/9/2021 ELAINE LEI
Building over 36-ft Cleared 4/5/2021 CALOSHA APPROVED
GPI Written Notices Cleared 6/24/2021 RODNEY SAMIIAN
Grading Pre-Inspection Cleared 6/24/2021 RODNEY SAMIIAN
Green Code Cleared 7/6/2021 MICHAEL AYERS
Fire Marshal Fire Life Safety Cleared 8/25/2021 VIDAL GARCIA
Low Impact Development Cleared 9/23/2021 MARTIN FRAGOSO
Density Bonus 12.22.A.31 Cleared 11/29/2021 MARITESS GO
Frnt yard landscape/Water mgmt Cleared 12/20/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/20/2021 MIGUEL GAMBOA
Miscellaneous Cleared 12/20/2021 MIGUEL GAMBOA
Opn space landscape/Water mgmt Cleared 12/20/2021 MIGUEL GAMBOA
Specific Plan Cleared 12/20/2021 MIGUEL GAMBOA
ZA Case Cleared 12/20/2021 MIGUEL GAMBOA
ZA Case Cleared 12/20/2021 MIGUEL GAMBOA
ZA Case Cleared 12/20/2021 MIGUEL GAMBOA
DAS Clearance Cleared 12/23/2021 RODNEY SAMIIAN
Roof/Waste drainage to street Cleared 2/3/2022 AMAAN MALIK
Hold Cleared 4/17/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504
Engineer Mehdizadehnasrabadi,, Mohammad; Lic. No.: C85373 388 E OCEAN BLVD APT 418      LONG BEACH, CA 90802

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/19/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/1/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/3/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/12/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/12/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/12/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/15/2023 Conditional Approval DAVID BURKHEAD
Green Building Rough 5/26/2023 No Access for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/26/2023 No Access for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/26/2023 No Access for Inspection EDWIN GREGORYONA
Green Building Rough 6/15/2023 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/15/2023 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/15/2023 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 6/22/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 7/14/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 7/14/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/14/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/24/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Masonry Frame 7/24/2023 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/24/2023 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 9/21/2023 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 9/21/2023 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 9/21/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/21/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 9/25/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 9/26/2023 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 9/26/2023 Not Ready for Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 10/10/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 No Access for Inspection EDWIN GREGORYONA
Green Building Rough 12/5/2023 No Access for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/5/2023 No Access for Inspection EDWIN GREGORYONA
Wood Frame 12/5/2023 No Access for Inspection EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/8/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 1/8/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 1/8/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 1/8/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 1/31/2024 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 1/31/2024 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/31/2024 Partial Approval RAFAEL CORTES
Special/Order Compliance 2/1/2024 No Access for Inspection RAFAEL CORTES
Special/Order Compliance 2/2/2024 Corrections Issued RAFAEL CORTES
Green Building Rough 2/12/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/12/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/12/2024 Partial Inspection DAVID BURKHEAD
Green Building Rough 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/22/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/22/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 3/4/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/4/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/4/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 3/11/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/11/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/11/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 3/18/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/18/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/18/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 3/27/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 3/27/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 3/27/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 5/10/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/10/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/10/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 5/14/2024 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 5/14/2024 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 5/14/2024 Conditional Approval LARRY ARNICK
Verify Sprinkler Sign Off 5/14/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 5/14/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/16/2024 Partial Inspection DAVID BURKHEAD
Green Building Rough 5/16/2024 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 5/16/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/16/2024 Partial Approval DAVID BURKHEAD
Wood Frame 5/16/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 6/18/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 6/18/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 6/18/2024 Partial Approval DAVID BURKHEAD
Wood Frame 6/18/2024 Partial Inspection DAVID BURKHEAD
Insulation 6/21/2024 Partial Inspection DAVID BURKHEAD
Drywall Nailing 7/2/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 7/2/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 7/2/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 7/2/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 7/2/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/9/2024 Not Ready for Inspection DAVID BURKHEAD
Interior/Exterior Lathing 7/9/2024 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 7/9/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/9/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 7/16/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 7/16/2024 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 7/16/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 7/16/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/5/2024 Not Ready for Inspection DAVID BURKHEAD
Green Building Rough 8/5/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/5/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/5/2024 Partial Approval DAVID BURKHEAD
Wood Frame 8/5/2024 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 8/9/2024 Conditional Approval DAVID BURKHEAD
Green Building Rough 8/9/2024 Not Ready for Inspection DAVID BURKHEAD
Insulation 8/9/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 8/9/2024 Partial Approval DAVID BURKHEAD
Wood Frame 8/9/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 8/12/2024 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 8/26/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/30/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 9/6/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/13/2024 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 9/13/2024 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 9/24/2024 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 9/25/2024 Corrections Issued DAVID BURKHEAD
Light Gage Steel Frame 10/11/2024 Partial Approval DAVID BURKHEAD
Light Gage Steel Frame 12/13/2024 Partial Approval DAVID BURKHEAD
Pre-Inspection 12/23/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 12/30/2024 Partial Approval EDWIN GREGORYONA
Pre-Inspection 3/25/2025 Approved DAVID BURKHEAD
Pre-Inspection 5/14/2025 Approved DAVID BURKHEAD
Pre-Inspection 6/3/2025 Approved DAVID BURKHEAD
Special/Order Compliance 6/18/2025 Partial Approval EDWIN GREGORYONA
Pre-Inspection 6/26/2025 Partial Inspection DAVID BURKHEAD
Pre-Inspection 7/30/2025 Approved DAVID BURKHEAD
Pre-Inspection 1/5/2026 Partial Inspection DAVID BURKHEAD
Pre-Inspection 1/15/2026 Partial Inspection DAVID BURKHEAD
Drywall Nailing 1/27/2026 Approved DAVID BURKHEAD
Final 1/27/2026 OK to Issue CofO DAVID BURKHEAD
Footing/Foundation/Slab 1/27/2026 Approved DAVID BURKHEAD
Green Building Final 1/27/2026 Approved DAVID BURKHEAD
Green Building Rough 1/27/2026 Approved DAVID BURKHEAD
Reinforced Concrete Frame 1/27/2026 Approved DAVID BURKHEAD
Reinforced Masonry Frame 1/27/2026 Approved DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 1/27/2026 Approved DAVID BURKHEAD
Structural Steel Frame 1/27/2026 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 1/27/2026 Approved DAVID BURKHEAD
Wood Frame 1/27/2026 Approved DAVID BURKHEAD