14083 W LA RUE ST 91340

Certificate Information: 14083 W LA RUE ST 91340

Application / Permit
20010-20000-03056
Plan Check / Job No.
B20VN11701
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A33(C)(E), ALL WORK PER WFPP
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 RARES BODEA
Corrections Issued 9/27/2020 RARES BODEA
Building Plans Picked Up 10/1/2020 APPLICANT
Applicant returned to address corrections 10/30/2020 RARES BODEA
Plan Check Approved 11/19/2020 RARES BODEA
Issued 12/30/2020 APPLICANT
CofO in Progress 1/13/2022 JENNIFER RABUCHIN
Permit Finaled 1/22/2022 MICHAEL SMITH
CofO Issued 1/22/2022 MICHAEL SMITH
Permit Finaled 1/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Address approval Cleared 9/30/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/5/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/5/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 11/8/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/9/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2021 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/30/2021 Corrections Issued CHARLES POWELL
Green Building Rough 6/30/2021 Not Ready for Inspection CHARLES POWELL
METHANE-Rough 6/30/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 6/30/2021 Corrections Issued CHARLES POWELL
Verify Sprinkler Sign Off 6/30/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/6/2021 Partial Approval JENNIFER RABUCHIN
Insulation 7/6/2021 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 7/6/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/6/2021 Partial Approval JENNIFER RABUCHIN
Sewer 7/6/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 7/6/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval JENNIFER RABUCHIN
Insulation 7/7/2021 Partial Approval JENNIFER RABUCHIN
Sewer 7/7/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/29/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/29/2021 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 7/29/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 7/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 7/29/2021 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 7/29/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/10/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/10/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 8/10/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/10/2021 Approved JENNIFER RABUCHIN
Insulation 8/17/2021 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 8/17/2021 Partial Approval MISAEL ESPARZA
Shower Pan 8/17/2021 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 8/23/2021 Approved JENNIFER RABUCHIN
Green Building Rough 8/23/2021 Approved JENNIFER RABUCHIN
Shower Pan 8/23/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/31/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 10/13/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Final 11/23/2021 Corrections Issued JENNIFER RABUCHIN
Final 11/23/2021 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 11/23/2021 Approved JENNIFER RABUCHIN
Green Building Final 11/23/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 11/23/2021 Corrections Issued JENNIFER RABUCHIN
METHANE-Barrier 11/23/2021 Approved JENNIFER RABUCHIN
METHANE-Subgrade 11/23/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/23/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/23/2021 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 11/23/2021 Approved JENNIFER RABUCHIN
Final 12/2/2021 Corrections Issued MICHAEL TEMPLE
Gas Test 12/2/2021 Approved MICHAEL TEMPLE
Green Building Final 12/2/2021 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Approved MICHAEL TEMPLE
Service/Power Release 12/2/2021 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Final 1/13/2022 Approved JENNIFER RABUCHIN
Final 1/13/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 1/13/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/13/2022 Approved JENNIFER RABUCHIN
Service/Power Release 1/13/2022 Approved JENNIFER RABUCHIN