14083 W LA RUE ST 91340
Certificate Information: 14083 W LA RUE ST 91340
- Application / Permit
- 20010-20000-03056
- Plan Check / Job No.
- B20VN11701
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 20' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A33(C)(E), ALL WORK PER WFPP
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | RARES BODEA |
| Corrections Issued | 9/27/2020 | RARES BODEA |
| Building Plans Picked Up | 10/1/2020 | APPLICANT |
| Applicant returned to address corrections | 10/30/2020 | RARES BODEA |
| Plan Check Approved | 11/19/2020 | RARES BODEA |
| Issued | 12/30/2020 | APPLICANT |
| CofO in Progress | 1/13/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 9/30/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/5/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 11/8/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/9/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/30/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 6/30/2021 | Not Ready for Inspection | CHARLES POWELL |
| METHANE-Rough | 6/30/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 6/30/2021 | Corrections Issued | CHARLES POWELL |
| Verify Sprinkler Sign Off | 6/30/2021 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/7/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 7/7/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 7/29/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/29/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/10/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/10/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/10/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/17/2021 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/17/2021 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 8/17/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 8/23/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/23/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 8/23/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/31/2021 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 10/13/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/23/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/23/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 11/23/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 11/23/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 11/23/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 11/23/2021 | Approved | JENNIFER RABUCHIN |
| Final | 12/2/2021 | Corrections Issued | MICHAEL TEMPLE |
| Gas Test | 12/2/2021 | Approved | MICHAEL TEMPLE |
| Green Building Final | 12/2/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Service/Power Release | 12/2/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| ELECTRICAL-Final | 1/13/2022 | Approved | JENNIFER RABUCHIN |
| Final | 1/13/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/13/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/13/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/13/2022 | Approved | JENNIFER RABUCHIN |