6301 N SUNNYSLOPE AVE 91401

Certificate Information: 6301 N SUNNYSLOPE AVE 91401

Application / Permit
20010-20000-03054
Plan Check / Job No.
B20VN11694
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) IRREGULAR SHAPED 53' X 37' SINGLE FAMILY DWELLING WITH ATTACHED (N) 20'-6" X 19' GARAGE AND 20' X 9'-6" ATTACHED TRELLIS ALL WORK PER ENGINEERING PER PARCEL MAP SUBDIVISION AA-2019-6365 PMLA NFPA 13D FIRE SPRINKLERS REQUIRED
Permit Issued
Issued on 2/23/2022
Issuing Office
Current Status
CofO Issued on 10/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 RODNEY SAMIIAN
Corrections Issued 9/16/2020 RODNEY SAMIIAN
Quality Review Completed 9/17/2020 CHON CHIO KUO
Plan Check Approved 2/14/2022 SEWADA ZADOORAN MILAGARDI
Issued 2/23/2022 APPLICANT
CofO in Progress 9/11/2023 KIRK SANDERS
Permit Finaled 10/28/2023 RUBEN SALAS
CofO Issued 10/28/2023 RUBEN SALAS
Permit Finaled 10/28/2023 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/1/2021 MARTIN FRAGOSO
Address approval Cleared 12/9/2021 CARLOS AGUILERA
Permit Cleared 12/9/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/9/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/14/2021 CARLOS AGUILERA
Sewer availability Cleared 12/14/2021 CARLOS AGUILERA
Miscellaneous Cleared 12/20/2021 MIGUEL GAMBOA
Tract Map conditions Cleared 12/20/2021 MIGUEL GAMBOA

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Higbee,, Scott Parker; Lic. No.: C52362 2625 EAST CLAYS ALLEY      TUCSON, AZ 85716

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/4/2022 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 3/17/2022 Approved MATT KELLERMAN
Footing/Foundation/Slab 3/17/2022 Approved MATT KELLERMAN
Deputy Reinf. Concrete 3/23/2022 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 3/31/2022 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 3/31/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/31/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/2/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 6/2/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 6/2/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/8/2022 Partial Inspection CHRISTOPHE COCHRAN
Insulation 6/15/2022 Conditional Approval RAFAEL CORTES
Interior/Exterior Lathing 6/15/2022 Approved RAFAEL CORTES
Drywall Nailing 6/23/2022 Corrections Issued RAFAEL CORTES
Drywall Nailing 5/19/2023 Approved KIRK SANDERS
ELECTRICAL-Final 5/19/2023 Corrections Issued KIRK SANDERS
Final 5/19/2023 Corrections Issued KIRK SANDERS
Green Building Final 5/19/2023 Approved KIRK SANDERS
HVAC-Final 5/19/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 5/19/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Approved KIRK SANDERS
Service/Power Release 5/19/2023 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 5/19/2023 Approved KIRK SANDERS
ELECTRICAL-Final 5/26/2023 Approved KIRK SANDERS
Final 5/26/2023 Corrections Issued KIRK SANDERS
HVAC-Final 5/26/2023 Approved KIRK SANDERS
PLUMBING-Final 5/26/2023 Approved KIRK SANDERS
Service/Power Release 5/26/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 9/8/2023 Approved KIRK SANDERS
Final 9/8/2023 OK to Issue CofO KIRK SANDERS
HVAC-Final 9/8/2023 Approved KIRK SANDERS
PLUMBING-Final 9/8/2023 Approved KIRK SANDERS
Service/Power Release 9/8/2023 Approved KIRK SANDERS