12500 N SADDLE CT 91326
Certificate Information: 12500 N SADDLE CT 91326
- Application / Permit
- 20010-20000-03047
- Plan Check / Job No.
- B20VN11686
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SFD W/ ATTACHED GARAGE PER LA CITY STANDARD PLAN #654 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/3/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/8/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/8/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/8/2020 | APPLICANT |
| Plan Check Approved | 11/24/2020 | NILOOFAR MEHRAIN |
| Issued | 11/3/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | JEFFREY PARD |
| Permit Finaled | 9/29/2022 | MICHAEL SMITH |
| CofO Issued | 9/29/2022 | MICHAEL SMITH |
| Permit Finaled | 9/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/21/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 11/2/2020 | AMMAR ELTAWIL |
| Address approval | Cleared | 11/5/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | LEE GUILBEAUX |
| Permit | Cleared | 11/5/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/5/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/5/2020 | LEE GUILBEAUX |
| "T" removal | Cleared | 11/9/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 11/9/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 11/9/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 11/9/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 11/9/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 11/9/2020 | DENZEL HENDERSON |
| ZI | Cleared | 11/9/2020 | DENZEL HENDERSON |
| Disturb/Remove Protected Trees | Cleared | 11/13/2020 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 12/10/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 10/27/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 10/27/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/22/2021 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 1/14/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | HENRY KIM |
| Deputy Reinf. Concrete | 1/18/2022 | Approved | SEAN WIRCH |
| Sewer | 2/24/2022 | Approved | HENRY KIM |
| Underground Mechanical | 3/8/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | HENRY KIM |
| Deputy Wood Construction | 4/13/2022 | Conditional Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 4/19/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 5/4/2022 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 5/4/2022 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Partial Approval | HENRY KIM |
| HVAC-Rough | 5/4/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | HENRY KIM |
| Green Building Rough | 5/11/2022 | Approved | HENRY KIM |
| PLUMBING-Rough | 5/11/2022 | Approved | HENRY KIM |
| Verify Sprinkler Sign Off | 5/11/2022 | Approved | HENRY KIM |
| Drywall Nailing | 5/20/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/31/2022 | Approved | HENRY KIM |
| Gas Test | 7/8/2022 | Corrections Issued | HENRY KIM |
| Gas Test | 7/12/2022 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Approved | HENRY KIM |
| Service/Power Release | 8/5/2022 | Approved | HENRY KIM |
| Smoke Detectors | 8/5/2022 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 9/6/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 9/6/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 9/6/2022 | Approved | JEFFREY PARD |
| Final | 9/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 9/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 9/7/2022 | Not Ready for Inspection | JEFFREY PARD |
| Final | 9/15/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 9/15/2022 | Approved | JEFFREY PARD |
| Smoke Detectors | 9/15/2022 | Approved | JEFFREY PARD |