8940 N GLENOAKS BLVD 91352

Certificate Information: 8940 N GLENOAKS BLVD 91352

Application / Permit
20010-20000-03040
Plan Check / Job No.
B20VN11684
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(17) Restaurant - Drive Through Fast Food
Work Description
(N) 1-STORY TYPE V-B DRIVE-THRU FAST FOOD RESTAURANT PER ZA-2017-3684-CU-SPP-SPR (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 9/22/2021
Issuing Office
Valley
Current Status
Issued on 9/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Disabled Access Plans Picked Up 9/21/2020 APPLICANT
Green Plans Picked Up 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 NILOOFAR MEHRAIN
Corrections Issued 10/6/2020 NILOOFAR MEHRAIN
Quality Review Completed 10/6/2020 CHON CHIO KUO
Building Plans Picked Up 10/6/2020 APPLICANT
Applicant returned to address corrections 1/19/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/11/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/3/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/27/2021 NILOOFAR MEHRAIN
Plan Check Approved 8/31/2021 NILOOFAR MEHRAIN
Issued 9/22/2021 APPLICANT
TCO Issued (Expire Date: 04-26-2023) 10/28/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/18/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 12/7/2020 MATTHEW CRAIG
Address approval Cleared 12/10/2020 JOHN TRIANTAFYLLOS
Drive Through Cleared 12/21/2020 ALBERT ISAGULIAN
Driveway location Cleared 12/21/2020 ALBERT ISAGULIAN
Internal circulation Cleared 12/21/2020 ALBERT ISAGULIAN
Specific Plan Cleared 12/21/2020 ALBERT ISAGULIAN
Green Code Cleared 12/23/2020 AARON COSTA
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Food Service Establishment Cleared 2/16/2021 KENNETH BROWNE
DAS Clearance Cleared 2/18/2021 NILOOFAR MEHRAIN
GPI Written Notices Cleared 6/3/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 6/3/2021 NILOOFAR MEHRAIN
Low Impact Development Cleared 6/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/7/2021 GABRIEL ROBLES
Highway dedication Cleared 7/8/2021 GABRIEL ROBLES
Permit Cleared 7/12/2021 GABRIEL ROBLES
Comm Cor/Mini-Mall Cleared 8/19/2021 PABLO ESTRADA
Comm Cor/Mini-Mall Cleared 8/19/2021 PABLO ESTRADA
Prkng lot landscape/Water mgmt Cleared 8/19/2021 PABLO ESTRADA
Specific Plan Cleared 8/19/2021 PABLO ESTRADA
ZA Case Cleared 8/19/2021 PABLO ESTRADA
ZA Case Cleared 8/19/2021 PABLO ESTRADA
ZI Cleared 8/19/2021 PABLO ESTRADA
Food establishment approval Cleared 8/31/2021 LACDHS APPROVED

Contact Information

Contractor E P I Construction Inc; Lic. No.: 865616-B 12345 VENTURA BLVD SUITE H      STUDIO CITY, CA 91604
Engineer Chan,, Dominic Kam-Tim; Lic. No.: S4381 5147 GOLDEN WEST AVE      TEMPLE CITY, CA 91780

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/20/2021 Partial Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 10/21/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/22/2021 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/28/2021 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/1/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 11/4/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/5/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/5/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/9/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/12/2021 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval DANNY RODRIGUEZ
Green Building Rough 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 12/6/2021 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 12/7/2021 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 12/10/2021 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/10/2021 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 12/10/2021 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/13/2021 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/14/2021 No Access for Inspection DANNY RODRIGUEZ
Deputy Steel/Welding 12/15/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/16/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 12/17/2021 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 1/4/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/4/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/4/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 1/19/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 1/28/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 2/4/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 2/8/2022 Partial Approval DANNY RODRIGUEZ
Insulation 2/24/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 3/11/2022 Approved DANNY RODRIGUEZ
Pre-Inspection 3/11/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 3/17/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 3/30/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 3/30/2022 Not Ready for Inspection DANNY RODRIGUEZ
Final 5/24/2022 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 5/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 5/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 5/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 5/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Final 7/18/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/18/2022 Approved DANNY RODRIGUEZ
Green Building Final 7/18/2022 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/18/2022 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 7/18/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/18/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 7/18/2022 Partial Inspection DANNY RODRIGUEZ
Final 9/12/2022 Partial Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/12/2022 Approved DANNY RODRIGUEZ
Wood Frame 9/12/2022 Approved DANNY RODRIGUEZ
Final 10/28/2022 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 4/27/2023 Partial Inspection DANNY RODRIGUEZ