1016 N ILIFF ST 90272
Certificate Information: 1016 N ILIFF ST 90272
- Application / Permit
- 20010-20000-03033
- Plan Check / Job No.
- B20VN11660
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING W/ROOF DECK AND BASEMENT (38'-0"x71'-8") FIRE SPRINKLERS NFPA-13D
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofO Issued on 12/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/3/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/9/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Plan Check Approved | 3/15/2021 | MOHAMMAD ESMAILI |
| Issued | 3/15/2021 | APPLICANT |
| CofO in Progress | 11/18/2022 | KEVIN SARGSYAN |
| Permit Finaled | 12/2/2022 | DANIEL ORRANTE |
| CofO Issued | 12/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 10/30/2020 | CALOSHA APPROVED |
| Address approval | Cleared | 11/2/2020 | DINAH GARIN |
| Permit | Cleared | 11/2/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/5/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 12/10/2020 | JOHN KIM |
| Low Impact Development | Cleared | 1/13/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/13/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/15/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 3/10/2021 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 3/10/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2021 | Partial Inspection | JOHN KIDWELL |
| Underground Mechanical | 4/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 4/27/2021 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/12/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/12/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/25/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Reinforced Concrete Frame | 5/25/2021 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 5/25/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/16/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Rough | 9/9/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/20/2021 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/27/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 10/27/2021 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/27/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/5/2021 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 11/9/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 11/29/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/29/2021 | Not Ready for Inspection | ANDREW NAVE |
| Shower Pan | 11/29/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/30/2021 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 12/1/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 12/1/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/1/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/14/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/14/2021 | Approved | JOHN KIDWELL |
| Insulation | 12/14/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/14/2021 | Partial Approval | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 12/14/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/20/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/20/2021 | Partial Approval | JOHN KIDWELL |
| Sewer | 6/14/2022 | Approved | JOHN KIDWELL |
| Underground Mechanical | 6/14/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 10/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| Smoke Detectors | 10/31/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 11/3/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 11/3/2022 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 11/3/2022 | Approved | KEVIN SARGSYAN |
| Final | 11/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 11/4/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 11/4/2022 | Approved | KEVIN SARGSYAN |
| Reinforced Concrete Frame | 11/4/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 11/14/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 11/14/2022 | Approved | KEVIN SARGSYAN |
| Final | 11/18/2022 | OK to Issue CofO | KEVIN SARGSYAN |