20612 W OVERLOOK CT 91326

Certificate Information: 20612 W OVERLOOK CT 91326

Application / Permit
20010-20000-03030
Plan Check / Job No.
B20VN11633
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD/GARAGE - MODEL HOME. STD PLAN #655, PLAN 5CR ,TRACT 50505
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 CHON CHIO KUO
Corrections Issued 10/20/2020 CHON CHIO KUO
Quality Review Completed 10/23/2020 STEVEN KIM
Building Plans Picked Up 10/27/2020 APPLICANT
Applicant returned to address corrections 3/24/2021 CHON CHIO KUO
Applicant returned to address corrections 4/13/2021 CHON CHIO KUO
Plan Check Approved 4/15/2021 CHON CHIO KUO
Issued 4/15/2021 APPLICANT
TCO Issued (Expire Date: 02-11-2023) 8/15/2022 MICHAEL SMITH
CofO in Progress 8/30/2022 SEAN WIRCH
CofO Issued 10/26/2022 MICHAEL SMITH
Permit Finaled 10/26/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 12/14/2020 AMMAR ELTAWIL
Address approval Cleared 12/18/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/18/2020 LEE GUILBEAUX
Permit Cleared 12/18/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/18/2020 LEE GUILBEAUX
Sewer availability Cleared 12/18/2020 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 12/18/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 12/18/2020 LEE GUILBEAUX
"T" removal Cleared 12/21/2020 DENZEL HENDERSON
Tract Map conditions Cleared 12/21/2020 DENZEL HENDERSON
Hydrant and Access approval Cleared 2/6/2021 ROBERT DUFF
GPI Written Notices Cleared 3/24/2021 CHON CHIO KUO
Grading Pre-Inspection Cleared 3/24/2021 CHON CHIO KUO
ZI Cleared 3/25/2021 DENZEL HENDERSON

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034
Engineer Hattar,, Basil Ibrahim; Lic. No.: GE2734 41837 SONOMA ROAD      PALMDALE, CA 93551
Engineer Wong,, Ramon Roman; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2021 Approved SEAN WIRCH
METHANE-Barrier 5/17/2021 Approved SEAN WIRCH
METHANE-Subgrade 5/17/2021 Approved SEAN WIRCH
Deputy Reinf. Concrete 5/18/2021 Partial Approval SEAN WIRCH
Deputy Reinf. Concrete 5/19/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Approval SEAN WIRCH
HVAC-Rough 8/23/2021 Approved SEAN WIRCH
Special/Order Compliance 8/23/2021 Approved STEVEN BACK
PLUMBING-Rough 9/10/2021 Approved SEAN WIRCH
ELECTRICAL-Rough 9/16/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Not Ready for Inspection SEAN WIRCH
ELECTRICAL-Rough 9/21/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Approved SEAN WIRCH
BUILDING-Rough-Frame 9/29/2021 Not Ready for Inspection SEAN WIRCH
Green Building Rough 9/29/2021 Not Ready for Inspection SEAN WIRCH
METHANE-Rough 9/29/2021 Approved SEAN WIRCH
Verify Sprinkler Sign Off 9/29/2021 Not Ready for Inspection SEAN WIRCH
Interior/Exterior Lathing 10/4/2021 Corrections Issued SEAN WIRCH
BUILDING-Rough-Frame 10/7/2021 Approved SEAN WIRCH
Green Building Rough 10/7/2021 Approved SEAN WIRCH
Interior/Exterior Lathing 10/7/2021 Partial Approval SEAN WIRCH
Verify Sprinkler Sign Off 10/7/2021 Approved SEAN WIRCH
Drywall Nailing 10/22/2021 Approved SEAN WIRCH
Sewer 11/17/2021 Approved SEAN WIRCH
Interior/Exterior Lathing 11/22/2021 Approved HENRY KIM
Underground Mechanical 11/22/2021 Approved HENRY KIM
Gas Test 12/16/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Not Ready SEAN WIRCH
Service/Power Release 12/21/2021 Corrections Issued SEAN WIRCH
Special/Order Compliance 12/21/2021 Corrections Issued SEAN WIRCH
Service/Power Release 1/5/2022 Approved SEAN WIRCH
Pre-Inspection 2/3/2022 Corrections Issued SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Not Ready SEAN WIRCH
ELECTRICAL-Final 3/17/2022 Approved SEAN WIRCH
HVAC-Final 3/17/2022 Approved SEAN WIRCH
PLUMBING-Final 3/17/2022 Approved SEAN WIRCH
Final 3/23/2022 OK for TCO SEAN WIRCH
Green Building Final 3/23/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved SEAN WIRCH
Smoke Detectors 3/23/2022 Approved SEAN WIRCH
ELECTRICAL-Final 8/29/2022 Approved SEAN WIRCH
Final 8/29/2022 OK to Issue CofO SEAN WIRCH
HVAC-Final 8/29/2022 Approved SEAN WIRCH
PLUMBING-Final 8/29/2022 Approved SEAN WIRCH
ELECTRICAL-Final 10/25/2022 Approved SEAN WIRCH
HVAC-Final 10/25/2022 Approved SEAN WIRCH
PLUMBING-Final 10/25/2022 Approved SEAN WIRCH