10642 W JIMENEZ ST 91342
Certificate Information: 10642 W JIMENEZ ST 91342
- Application / Permit
- 20010-20000-02997
- Plan Check / Job No.
- B20VN11559
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31'-2" X 39'-2" 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.21 A33. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | SERGIO MUNIZ |
| Corrections Issued | 9/30/2020 | SERGIO MUNIZ |
| Quality Review Completed | 10/15/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/23/2020 | APPLICANT |
| Applicant returned to address corrections | 12/27/2020 | SERGIO MUNIZ |
| Plan Check Approved | 1/10/2021 | SERGIO MUNIZ |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 12/28/2022 | WILLIAM WREN |
| CofO Issued | 1/18/2023 | MICHAEL SMITH |
| Permit Finaled | 1/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 10/26/2020 | PEGGY MALONE-BROWN |
| Grading Pre-Inspection | Cleared | 11/19/2020 | BRIAN MILLER |
| Low Impact Development | Cleared | 11/25/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 12/4/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/4/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 12/8/2020 | ROSE MARIE SMITH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2021 | Approved | MATTHEW NELSON |
| Underground Mechanical | 6/7/2021 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2021 | No Access for Inspection | MATTHEW NELSON |
| Underground Mechanical | 6/16/2021 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 6/18/2021 | Partial Inspection | DAVID SANDOVAL |
| Sewer | 6/18/2021 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 6/23/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/5/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/5/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 8/5/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 8/5/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Rough | 8/5/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 8/5/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 8/5/2021 | Approved | WILLIAM KUEHN |
| Insulation | 8/18/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 8/19/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/19/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 8/24/2021 | Conditional Approval | JAVIER RAMOS JR |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 8/24/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/8/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Shower Pan | 9/8/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/10/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 9/10/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 10/20/2022 | Approved | MATTHEW NELSON |
| Final | 10/20/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/20/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/20/2022 | Approved | MATTHEW NELSON |
| MERV13>=Final | 10/20/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 10/20/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 10/20/2022 | Approved | MATTHEW NELSON |
| Final | 11/7/2022 | No Access for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 11/7/2022 | No Access for Inspection | MATTHEW NELSON |
| Final | 11/17/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 11/17/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 12/8/2022 | Corrections Issued | WILLIAM WREN |
| Final | 12/22/2022 | OK to Issue CofO | WILLIAM WREN |
| Service/Power Release | 12/22/2022 | Approved | WILLIAM WREN |