7677 N GLENCREST DR 91504

Certificate Information: 7677 N GLENCREST DR 91504

Application / Permit
20010-20000-02996
Plan Check / Job No.
B20VN11556
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-5" X 32'-4" IRREGULAR SHAPE 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A33. [SEE COMMENTS].
Permit Issued
Issued on 7/3/2021
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SERGIO MUNIZ
Corrections Issued 10/5/2020 SERGIO MUNIZ
Quality Review Completed 10/23/2020 OMID HEDAYAT
Applicant returned to address corrections 3/10/2021 SERGIO MUNIZ
Applicant returned to address corrections 3/31/2021 SERGIO MUNIZ
Applicant returned to address corrections 6/8/2021 SERGIO MUNIZ
Plan Check Approved 6/22/2021 SERGIO MUNIZ
Issued 7/3/2021 APPLICANT
Building Plans Picked Up 7/9/2021 APPLICANT
CofO in Progress 8/5/2022 DAVID ANDERSON
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/20/2020 PATRICK MISCHLICH
Address approval Cleared 1/20/2021 ADRIAN CASTRO
Low Impact Development Cleared 1/20/2021 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 1/22/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/22/2021 ADRIAN CASTRO
Sewer availability Cleared 1/22/2021 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/8/2021 JEREMY CARTER

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/29/2021 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 8/2/2021 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 11/10/2021 Approved WILLIAM KUEHN
Sewer 11/10/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 12/13/2021 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Inspection WILLIAM KUEHN
Green Building Rough 12/13/2021 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Rough 12/13/2021 Not Ready for Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 12/13/2021 Not Ready for Inspection WILLIAM KUEHN
Drywall Nailing 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
Final 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Partial Inspection WILLIAM KUEHN
Green Building Final 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
Green Building Rough 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Final 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Rough 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Not Ready WILLIAM KUEHN
Service/Power Release 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
Smoke Detectors 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 12/17/2021 Not Ready for Inspection WILLIAM KUEHN
ELECTRICAL-Rough 12/21/2021 Approved WILLIAM KUEHN
Gas Test 12/21/2021 Approved WILLIAM KUEHN
HVAC-Rough 12/21/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 12/21/2021 Partial Approval WILLIAM KUEHN
PLUMBING-Rough 12/21/2021 Approved WILLIAM KUEHN
Drywall Nailing 1/7/2022 Not Ready for Inspection JOHN HAYES
Gas Test 1/7/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/7/2022 Not Ready for Inspection JOHN HAYES
Insulation 1/7/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 1/7/2022 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 1/7/2022 Corrections Issued JOHN HAYES
Drywall Nailing 1/25/2022 Approved MATTHEW NELSON
Green Building Rough 1/25/2022 Approved MATTHEW NELSON
Insulation 1/25/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 2/1/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/17/2022 Approved GREGG CUMMINGS
Final 6/17/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 6/17/2022 Approved GREGG CUMMINGS
MERV13>=Final 6/17/2022 Approved GREGG CUMMINGS
MERV13>=Rough 6/17/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 6/17/2022 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 6/17/2022 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 6/17/2022 Approved GREGG CUMMINGS
Final 7/7/2022 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved DAVID ANDERSON
Service/Power Release 7/7/2022 Not Ready for Inspection DAVID ANDERSON
Final 8/5/2022 OK to Issue CofO DAVID ANDERSON