647 S HUDSON AVE 90005

Certificate Information: 647 S HUDSON AVE 90005

Application / Permit
20010-20000-02992
Plan Check / Job No.
B20VN11533
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW DETACHED 537 SQ. FT. POOL CABANA . PER ENGINEERING DESIGN.
Permit Issued
Issued on 2/9/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 ALFREDO JARA
Corrections Issued 9/14/2020 ALFREDO JARA
Applicant returned to address corrections 11/5/2020 ALFREDO JARA
Plan Check Approved 2/2/2021 ALFREDO JARA
Issued 2/9/2021 APPLICANT
Building Plans Picked Up 2/9/2021 APPLICANT
CofO in Progress 12/28/2022 DEROLD HAUFF
Permit Finaled 1/3/2023 DEROLD HAUFF
CofO Issued 1/3/2023 DEROLD HAUFF
Permit Finaled 1/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 11/4/2020 ROBIN YAMADA
CPC Cleared 11/9/2020 SUKI GERSHENHORN
CPC Cleared 11/9/2020 SUKI GERSHENHORN
CPC Cleared 11/9/2020 SUKI GERSHENHORN
HPOZ Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Miscellaneous Cleared 11/9/2020 SUKI GERSHENHORN
Specific Plan Cleared 11/9/2020 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 12/10/2020 CELINA MORENO
Sewer availability Cleared 12/10/2020 CELINA MORENO
Miscellaneous Cleared 12/14/2020 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 12/21/2020 CELINA MORENO
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG

Contact Information

Contractor Ceilbright Services Inc; Lic. No.: 957706-B 9230 W OLYMPIC BLVD      BEVERLY HILLS, CA 90212

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/18/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 3/24/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/24/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 4/7/2021 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/13/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/3/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 5/3/2021 Approved JOSEPH MCGARRY
Green Building Rough 5/3/2021 Approved JOSEPH MCGARRY
METHANE-Rough 5/3/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/3/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/3/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 6/22/2021 Approved ALFREDO BALANDRA
Drywall Nailing 12/10/2021 Approved ARTHUR SARGSYAN
Final 12/10/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 12/10/2021 Approved ARTHUR SARGSYAN
Green Building Final 12/10/2021 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Subgrade 12/10/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved ARTHUR SARGSYAN
Service/Power Release 12/10/2021 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 12/10/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 4/4/2022 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 4/4/2022 Not Ready for Inspection ARTHUR SARGSYAN
Service/Power Release 4/4/2022 Not Ready for Inspection ARTHUR SARGSYAN
Smoke Detectors 4/4/2022 Not Ready for Inspection ARTHUR SARGSYAN
Final 6/8/2022 Not Ready for Inspection ADAM ESCOTO
Green Building Final 6/8/2022 Not Ready for Inspection ADAM ESCOTO
Service/Power Release 6/8/2022 Not Ready for Inspection ADAM ESCOTO
Smoke Detectors 6/8/2022 Not Ready for Inspection ADAM ESCOTO
Final 10/6/2022 Conditional Approval MICHAEL LEWIS
Green Building Final 10/6/2022 Approved MICHAEL LEWIS
Service/Power Release 10/6/2022 Approved MICHAEL LEWIS
Smoke Detectors 10/6/2022 Approved MICHAEL LEWIS
Final 11/17/2022 Conditional Approval RONALD MYRICK