823-825 1/2 N JUNE ST 90038

Certificate Information: 823-825 1/2 N JUNE ST 90038

Application / Permit
20010-20000-02972
Plan Check / Job No.
B20VN11471
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 96'10" X 37'11" THREE STORY 4 UNITS APARTMENT BUILDING (TYPE V A) OVER GARAGE (TYPE V-A) , NFPA-13 FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
Issued on 7/14/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Disabled Access Plans Picked Up 9/15/2020 APPLICANT
Green Plans Picked Up 9/15/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 RARES BODEA
Corrections Issued 10/2/2020 RARES BODEA
Quality Review Completed 10/6/2020 STEVEN KIM
Building Plans Picked Up 10/7/2020 APPLICANT
Applicant returned to address corrections 5/10/2021 RARES BODEA
Plan Check Approved 6/17/2021 RARES BODEA
Issued 7/14/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/4/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 11/4/2020 RENZ SORIANO
Highway dedication Cleared 11/4/2020 RENZ SORIANO
Permit Cleared 11/4/2020 RENZ SORIANO
Work Adjacent to Public Way Cleared 12/1/2020 ARMEN SARKISIAN
Low Impact Development Cleared 12/18/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/7/2021 CECILIO NAVARRO
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Green Code Cleared 1/15/2021 AARON COSTA
Sewer availability Cleared 3/11/2021 JEANIE LAM
Hydrant and Access approval Cleared 3/29/2021 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 3/31/2021 VIDAL GARCIA
Methane Ordinance Cleared 3/31/2021 VIDAL GARCIA
DAS Clearance Cleared 4/22/2021 RARES BODEA
Frnt yard landscape/Water mgmt Cleared 4/22/2021 DANG NGUYEN

Contact Information

Architect Mac, Laren, Michael Bruce; Lic. No.: C29858 23705 VANOWEN # 309      WEST HILLS, CA 91307
Contractor Ocean Construction; Lic. No.: 833486-B 1061 NORTH SPAULDING AVENUE      LOS ANGELES, CA 90046
Engineer Rubeiz,, Nadim Michel; Lic. No.: C69454 22711 CALIFA ST      WOODLAND HILLS, CA 91367
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 10/21/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/21/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 11/18/2021 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 11/18/2021 Partial Inspection EDWIN GREGORYONA
METHANE-Subgrade 11/18/2021 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Concrete 11/24/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 12/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/12/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 8/25/2022 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 12/1/2022 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 4/25/2023 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 4/25/2023 Approved EDWIN GREGORYONA
Light Gage Steel Frame 4/25/2023 Partial Inspection EDWIN GREGORYONA
METHANE-Rough 4/25/2023 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 4/25/2023 Approved EDWIN GREGORYONA
Drywall Nailing 5/18/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Not Ready for Inspection EDWIN GREGORYONA
Wall Anchors 5/18/2023 Approved EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval EDWIN GREGORYONA
Insulation 6/6/2023 Approved EDWIN GREGORYONA
Deputy Wood Construction 8/8/2023 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Partial Approval EDWIN GREGORYONA
Drywall Nailing 8/29/2023 Approved EDWIN GREGORYONA
Final 4/17/2025 Partial Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 4/17/2025 Approved EDWIN GREGORYONA
Green Building Final 4/17/2025 Approved EDWIN GREGORYONA
METHANE-Barrier 4/17/2025 Approved EDWIN GREGORYONA
METHANE-Subgrade 4/17/2025 Approved EDWIN GREGORYONA
Reinforced Concrete Frame 4/17/2025 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 4/17/2025 Approved EDWIN GREGORYONA
Wood Frame 4/17/2025 Approved EDWIN GREGORYONA
Final 7/23/2025 Corrections Issued EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Ready EDWIN GREGORYONA
Special/Order Compliance 7/23/2025 Approved EDWIN GREGORYONA
Pre-Inspection 12/19/2025 Approved EDWIN GREGORYONA