4213 N HAZELTINE AVE 91423
Certificate Information: 4213 N HAZELTINE AVE 91423
- Application / Permit
- 20010-20000-02970
- Plan Check / Job No.
- B20VN11462
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 37'-10" X 88'-1" (2)-STORY SFD WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/17/2020 | SELLA BENYAMIN |
| Quality Review Completed | 9/18/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/18/2020 | APPLICANT |
| Plan Check Approved | 1/26/2021 | SELLA BENYAMIN |
| Issued | 2/11/2021 | APPLICANT |
| CofO in Progress | 4/18/2022 | MATT KELLERMAN |
| Permit Finaled | 4/18/2022 | MICHAEL SMITH |
| CofO Issued | 4/18/2022 | MICHAEL SMITH |
| Permit Finaled | 4/18/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/2/2020 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | JOHN LIN |
| Permit | Cleared | 12/11/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 12/11/2020 | JOHN LIN |
| Sewer availability | Cleared | 12/11/2020 | JOHN LIN |
| Trees in Parkway | Cleared | 12/16/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Raub Doug Design & Development Inc; Lic. No.: 723625-B | 14066 ROBLAR ROAD SHERMAN OAKS, CA 91423 |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/18/2021 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 2/18/2021 | Not Ready for Inspection | CHARLES POWELL |
| Underground Mechanical | 2/18/2021 | Not Ready for Inspection | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 3/2/2021 | Partial Approval | CHARLES POWELL |
| Underground Mechanical | 3/2/2021 | Approved | CHARLES POWELL |
| Deputy Other (see comments) | 3/11/2021 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 3/11/2021 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 3/12/2021 | Partial Approval | CHARLES POWELL |
| Deputy Wood Construction | 5/12/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/26/2021 | Approved | CHARLES POWELL |
| HVAC-Rough | 5/26/2021 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 5/27/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 5/27/2021 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 6/3/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/3/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 6/11/2021 | Not Ready for Inspection | CHARLES POWELL |
| Verify Sprinkler Sign Off | 6/11/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 6/17/2021 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/22/2021 | Approved | CHARLES POWELL |
| Insulation | 6/22/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 6/22/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 6/25/2021 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 8/10/2021 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 8/16/2021 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 11/1/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/8/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 2/14/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 2/17/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 2/17/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/23/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 2/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 3/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/18/2022 | Approved | MISAEL ESPARZA |
| Green Building Final | 3/18/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 3/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/18/2022 | Approved | MISAEL ESPARZA |
| Final | 3/30/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 3/30/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/12/2022 | Conditional Approval | MISAEL ESPARZA |
| Service/Power Release | 4/12/2022 | Approved | MISAEL ESPARZA |