4213 N HAZELTINE AVE 91423

Certificate Information: 4213 N HAZELTINE AVE 91423

Application / Permit
20010-20000-02970
Plan Check / Job No.
B20VN11462
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 37'-10" X 88'-1" (2)-STORY SFD WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 4/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 SELLA BENYAMIN
Corrections Issued 9/17/2020 SELLA BENYAMIN
Quality Review Completed 9/18/2020 STEVEN KIM
Building Plans Picked Up 9/18/2020 APPLICANT
Plan Check Approved 1/26/2021 SELLA BENYAMIN
Issued 2/11/2021 APPLICANT
CofO in Progress 4/18/2022 MATT KELLERMAN
Permit Finaled 4/18/2022 MICHAEL SMITH
CofO Issued 4/18/2022 MICHAEL SMITH
Permit Finaled 4/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 12/2/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 12/11/2020 JOHN LIN
Permit Cleared 12/11/2020 JOHN LIN
Roof/Waste drainage to street Cleared 12/11/2020 JOHN LIN
Sewer availability Cleared 12/11/2020 JOHN LIN
Trees in Parkway Cleared 12/16/2020 JOHN KIM
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG

Contact Information

Contractor Raub Doug Design & Development Inc; Lic. No.: 723625-B 14066 ROBLAR ROAD      SHERMAN OAKS, CA 91423
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2021 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 2/18/2021 Not Ready for Inspection CHARLES POWELL
Underground Mechanical 2/18/2021 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 3/2/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 3/2/2021 Partial Approval CHARLES POWELL
Underground Mechanical 3/2/2021 Approved CHARLES POWELL
Deputy Other (see comments) 3/11/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 3/11/2021 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 3/12/2021 Partial Approval CHARLES POWELL
Deputy Wood Construction 5/12/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 5/26/2021 Approved CHARLES POWELL
HVAC-Rough 5/26/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 5/27/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 5/27/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 5/27/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 6/3/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/3/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/11/2021 Approved CHARLES POWELL
Green Building Rough 6/11/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 6/11/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 6/17/2021 Partial Approval CHARLES POWELL
Green Building Rough 6/22/2021 Approved CHARLES POWELL
Insulation 6/22/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 6/22/2021 Approved CHARLES POWELL
Drywall Nailing 6/25/2021 Approved DAVID MATSON
Interior/Exterior Lathing 8/10/2021 Partial Approval ALAN MORELOS
Interior/Exterior Lathing 8/16/2021 Approved ALIZAH MAYAGOITIA
Gas Test 11/1/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 2/8/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/14/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 2/17/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 2/17/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 2/23/2022 Approved MISAEL ESPARZA
HVAC-Final 2/23/2022 Not Ready for Inspection MISAEL ESPARZA
Final 3/18/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/18/2022 Approved MISAEL ESPARZA
Green Building Final 3/18/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 3/18/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/18/2022 Approved MISAEL ESPARZA
Final 3/30/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/30/2022 Not Ready for Inspection MISAEL ESPARZA
Final 4/12/2022 Conditional Approval MISAEL ESPARZA
Service/Power Release 4/12/2022 Approved MISAEL ESPARZA