6744 N RADFORD AVE 91606
Certificate Information: 6744 N RADFORD AVE 91606
- Application / Permit
- 20010-20000-02966
- Plan Check / Job No.
- B20VN11385
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT W/ ATTACHED GARAGE PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | COLIN LOREDO |
| Corrections Issued | 10/2/2020 | COLIN LOREDO |
| Quality Review Completed | 10/14/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/16/2020 | APPLICANT |
| Plan Check Approved | 6/4/2021 | COLIN LOREDO |
| Issued | 7/6/2021 | APPLICANT |
| CofO in Progress | 2/16/2023 | JOHN HAYES |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/8/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 5/25/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/26/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/16/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/25/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/14/2022 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 3/14/2022 | Partial Approval | CALEB MEISTER |
| Sewer | 3/14/2022 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 3/16/2022 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 6/9/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/16/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 6/27/2022 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 7/8/2022 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 7/8/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/8/2022 | Approved | JOHN HAYES |
| Sewer | 7/8/2022 | Approved | JOHN HAYES |
| Deputy Wood Construction | 7/13/2022 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2022 | Approved | JOHN HAYES |
| Green Building Rough | 7/14/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 7/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/14/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 8/1/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/1/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/1/2022 | Approved | DAVID ANDERSON |
| Insulation | 9/14/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 10/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 10/14/2022 | Approved | JOHN HAYES |
| Shower Pan | 10/21/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/28/2022 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/25/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 1/25/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 1/27/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Final | 2/3/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/3/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/3/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 2/3/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 2/3/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 2/3/2023 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 2/15/2023 | Approved | JOHN HAYES |
| Final | 2/15/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/15/2023 | Approved | JOHN HAYES |
| HVAC-Final | 2/15/2023 | Approved | JOHN HAYES |
| PLUMBING-Final | 2/15/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/15/2023 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 2/15/2023 | Approved | JOHN HAYES |
| Smoke Detectors | 2/15/2023 | Approved | JOHN HAYES |