2621 N HUTTON DR 90210

Certificate Information: 2621 N HUTTON DR 90210

Application / Permit
20010-20000-02956
Plan Check / Job No.
B20VN11423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 68'-2" X 73'-7" 2-STORY SINGLE FAMILY DWELLLING WITH ATTACHED 3-CAR GARAGE AND PATIO COVERS. FIRE SPRINKLER REQUIRED NFPA-13D.
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SERGIO MUNIZ
Corrections Issued 10/7/2020 SERGIO MUNIZ
Quality Review Completed 10/29/2020 OMID HEDAYAT
Building Plans Picked Up 11/6/2020 APPLICANT
Applicant returned to address corrections 1/8/2021 SERGIO MUNIZ
Plan Check Approved 3/2/2021 SERGIO MUNIZ
Issued 3/22/2021 APPLICANT
CofO in Progress 4/30/2025 MEL KHACHATOURIAN
No Progress 5/5/2025 MICHAEL PELHAM
CofO in Progress 5/5/2025 MICHAEL PELHAM
CofO Issued 6/3/2025 RICHARD STEINBACH
Permit Finaled 6/3/2025 RICHARD STEINBACH

Permit Application Clearance Information

Trees in Parkway Cleared 10/20/2020 JOHN KIM
Address approval Cleared 10/22/2020 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 10/22/2020 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 10/22/2020 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 10/22/2020 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 10/22/2020 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 10/22/2020 CATHERINE ADROVER
Permit Cleared 10/22/2020 CATHERINE ADROVER
Sewer availability Cleared 10/22/2020 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 10/26/2020 RAYMOND MUGAMBWA
Low Impact Development Cleared 11/8/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/9/2020 CATHERINE ADROVER
Watercourse Cleared 11/17/2020 MAHELET GEBEYHU
Hydrant and Access approval Cleared 11/23/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 12/15/2020 SERGIO MUNIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Zarei,, Ahmad; Lic. No.: S4118 PO BOX 3374      RANCHO SANTA FE, CA 92067
Geologist Pongracz-Bartha,, Ed; Lic. No.: EG2370 12220 SPRING TRAIL      KAGEL CANYON, CA 91342

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/18/2021 Conditional Approval DANIEL ORRANTE
Piling/Pier/Caisson 8/18/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 8/25/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/29/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
FLOOD-Elevation Certificate 10/7/2021 Approved MATT KELLERMAN
Footing/Foundation/Slab 10/7/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 10/7/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/1/2021 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 11/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 11/24/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/9/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 2/22/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 2/23/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 2/24/2022 Conditional Approval MICHAEL PELHAM
Deputy Steel/Welding 2/25/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/31/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/28/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/1/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/17/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Rough 9/6/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 9/6/2022 Approved GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 9/6/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 9/19/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 9/21/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/13/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/20/2022 Approved CARLOS MATAMOROS
HVAC-Rough 10/20/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/25/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 10/28/2022 Approved EVAN COOPER
FLOOD-Proofing Certificate 10/28/2022 Approved EVAN COOPER
Green Building Rough 10/28/2022 Approved EVAN COOPER
Interior/Exterior Lathing 10/28/2022 Partial Approval EVAN COOPER
Verify Sprinkler Sign Off 10/28/2022 Approved EVAN COOPER
Insulation 11/22/2022 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 12/1/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 12/19/2022 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/19/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Gas Test 12/20/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 3/14/2025 Partial Approval SEAN HAUPT
PLUMBING-Final 3/14/2025 Corrections Issued SEAN HAUPT
Smoke Detectors 3/14/2025 Approved SEAN HAUPT
ELECTRICAL-Final 3/25/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 3/25/2025 Approved STEPHANIE SWANSON
HVAC-Final 3/25/2025 Corrections Issued STEPHANIE SWANSON
Structural Steel Frame 3/25/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 3/28/2025 Approved SEAN HAUPT
Final 3/28/2025 Corrections Issued SEAN HAUPT
Green Building Final 3/28/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/28/2025 SGSOV Approved SEAN HAUPT
Service/Power Release 3/28/2025 Approved SEAN HAUPT
Final 4/7/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 4/7/2025 Approved DANIEL VERA
Final 4/17/2025 Corrections Issued ARAM AVEDISIAN
Final 4/29/2025 OK to Issue CofO MEL KHACHATOURIAN
Special/Order Compliance 5/5/2025 Corrections Issued SEAN HAUPT
Special/Order Compliance 5/16/2025 Approved SEAN HAUPT