Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 8/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 MOHAMMAD ESMAILI
Corrections Issued 9/26/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/19/2020 STEVEN KIM
Building Plans Picked Up 10/20/2020 APPLICANT
Applicant returned to address corrections 11/15/2021 MOHAMMAD ESMAILI
Plan Check Approved 1/26/2022 MOHAMMAD ESMAILI
Issued 2/14/2022 APPLICANT
CofO in Progress 8/5/2025 JOSE MACIAS
Permit Finaled 8/7/2025 DEROLD HAUFF
CofO Issued 8/7/2025 DEROLD HAUFF
Permit Finaled 8/7/2025 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/12/2020 MATTHEW CRAIG
Address approval Cleared 6/15/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/28/2021 WALLIE JONG
Sewer availability Cleared 6/28/2021 WALLIE JONG
Low Impact Development Cleared 10/20/2021 MARCO SANCHEZ
CPC Cleared 10/22/2021 SUKI GERSHENHORN
HPOZ Cleared 10/22/2021 SUKI GERSHENHORN
Historic monument Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 10/22/2021 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 10/27/2021 THAN WIN

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: C32722 20812 VENTURA BLVD SUITE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 4/12/2022 Approved ARTHUR SARGSYAN
Underground Mechanical 4/12/2022 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 4/19/2022 Corrections Issued STUART CHAPMAN
METHANE-Barrier 4/19/2022 Approved STUART CHAPMAN
METHANE-Rough 4/19/2022 Approved STUART CHAPMAN
METHANE-Subgrade 4/19/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 4/21/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved ARTHUR SARGSYAN
Insulation 5/5/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 5/5/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/7/2022 Not Ready for Inspection ADAM ESCOTO
ELECTRICAL-Rough 6/7/2022 Approved ADAM ESCOTO
Green Building Rough 6/7/2022 Not Ready for Inspection ADAM ESCOTO
HVAC-Rough 6/7/2022 Approved ADAM ESCOTO
PLUMBING-Rough 6/7/2022 Corrections Issued ADAM ESCOTO
Verify Sprinkler Sign Off 6/7/2022 Not Ready for Inspection ADAM ESCOTO
Wood Frame 6/7/2022 Not Ready for Inspection ADAM ESCOTO
PLUMBING-Rough 6/13/2022 Approved ADAM ESCOTO
Wood Frame 9/20/2022 Approved MICHAEL LEWIS
Wood Frame 9/21/2022 Partial Inspection MICHAEL LEWIS
Insulation 10/19/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/19/2022 Approved MICHAEL LEWIS
Drywall Nailing 10/26/2022 Approved JOSEPH MCGARRY
Shower Pan 10/26/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/15/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/9/2023 Conditional Approval RICHARD DOCKUS
Final 11/9/2023 Corrections Issued RICHARD DOCKUS
Green Building Final 11/9/2023 Approved RICHARD DOCKUS
Green Building Rough 11/9/2023 Approved RICHARD DOCKUS
HVAC-Final 11/9/2023 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 11/9/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 1/4/2024 Approved RICHARD DOCKUS
PLUMBING-Final 1/4/2024 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 2/12/2025 Approved ENRIQUE MIRELES
Final 2/12/2025 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 2/12/2025 Not Ready for Inspection ENRIQUE MIRELES
Final 4/22/2025 Corrections Issued RONNIE MINDANAO
Service/Power Release 4/22/2025 Not Ready for Inspection RONNIE MINDANAO
Final 4/30/2025 Not Ready for Inspection RONNIE MINDANAO
Service/Power Release 4/30/2025 Corrections Issued RONNIE MINDANAO
Final 7/17/2025 Not Ready for Inspection RONNIE MINDANAO
Service/Power Release 7/17/2025 Not Ready for Inspection RONNIE MINDANAO
Final 7/29/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 7/29/2025 Approved JOSE MACIAS