17720 W SAN JOSE ST 91344
Certificate Information: 17720 W SAN JOSE ST 91344
- Application / Permit
- 20010-20000-02949
- Plan Check / Job No.
- B20VN11414
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1,200 SQ. FT. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit"
- Permit Issued
- Issued on 3/16/2023
- Issuing Office
- Current Status
- CofO Issued on 5/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | COLIN LOREDO |
| Corrections Issued | 10/2/2020 | COLIN LOREDO |
| Quality Review Completed | 10/19/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| Plan Check Approved | 3/14/2023 | SELLA BENYAMIN |
| Issued | 3/16/2023 | APPLICANT |
| CofO in Progress | 5/16/2025 | DAVID SCANTLIN |
| CofO Issued | 5/19/2025 | JOHN JANSON |
| Permit Finaled | 5/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/2/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 3/14/2023 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/2/2023 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/9/2023 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | DAVID SCANTLIN |
| Insulation | 3/20/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 3/20/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 3/28/2024 | No Access for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 3/28/2024 | No Access for Inspection | DAVID SCANTLIN |
| Insulation | 3/28/2024 | No Access for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/3/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/3/2024 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/3/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 4/3/2024 | Approved | DAVID SCANTLIN |
| Insulation | 4/3/2024 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/18/2024 | Approved | KRISTEN CAUSEY |
| Gas Test | 5/2/2024 | Approved | DAVID SCANTLIN |
| Sewer | 5/2/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 5/22/2024 | Partial Inspection | KRISTEN CAUSEY |
| Shower Pan | 6/6/2024 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 6/11/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/25/2025 | Approved | DAVID SCANTLIN |
| Final | 3/25/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 3/25/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 3/25/2025 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 3/25/2025 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 3/25/2025 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/25/2025 | Approved | DAVID SCANTLIN |
| Final | 5/14/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 5/14/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2025 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 5/14/2025 | Approved | DAVID SCANTLIN |
| Final | 5/16/2025 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 5/16/2025 | Approved | DAVID SCANTLIN |