17720 W SAN JOSE ST 91344

Certificate Information: 17720 W SAN JOSE ST 91344

Application / Permit
20010-20000-02949
Plan Check / Job No.
B20VN11414
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1,200 SQ. FT. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit"
Permit Issued
Issued on 3/16/2023
Issuing Office
Current Status
CofO Issued on 5/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 COLIN LOREDO
Corrections Issued 10/2/2020 COLIN LOREDO
Quality Review Completed 10/19/2020 STEVEN KIM
Building Plans Picked Up 10/21/2020 APPLICANT
Plan Check Approved 3/14/2023 SELLA BENYAMIN
Issued 3/16/2023 APPLICANT
CofO in Progress 5/16/2025 DAVID SCANTLIN
CofO Issued 5/19/2025 JOHN JANSON
Permit Finaled 5/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/2/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/2/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/14/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/2/2023 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 5/9/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/15/2023 Partial Approval DAVID SCANTLIN
Insulation 3/20/2024 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 3/20/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 3/28/2024 No Access for Inspection DAVID SCANTLIN
HVAC-Rough 3/28/2024 No Access for Inspection DAVID SCANTLIN
Insulation 3/28/2024 No Access for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 4/3/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 4/3/2024 Approved DAVID SCANTLIN
Green Building Rough 4/3/2024 Approved DAVID SCANTLIN
HVAC-Rough 4/3/2024 Approved DAVID SCANTLIN
Insulation 4/3/2024 Approved DAVID SCANTLIN
Drywall Nailing 4/18/2024 Approved KRISTEN CAUSEY
Gas Test 5/2/2024 Approved DAVID SCANTLIN
Sewer 5/2/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 5/22/2024 Partial Inspection KRISTEN CAUSEY
Shower Pan 6/6/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 6/11/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 3/25/2025 Approved DAVID SCANTLIN
Final 3/25/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 3/25/2025 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 3/25/2025 Approved DAVID SCANTLIN
PLUMBING-Final 3/25/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 3/25/2025 Approved DAVID SCANTLIN
Smoke Detectors 3/25/2025 Approved DAVID SCANTLIN
Final 5/14/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 5/14/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 5/14/2025 Approved DAVID SCANTLIN
Final 5/16/2025 OK to Issue CofO DAVID SCANTLIN