3340 W GARDEN AVE 90039
Certificate Information: 3340 W GARDEN AVE 90039
- Application / Permit
- 20010-20000-02947
- Plan Check / Job No.
- B20VN11413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF A 2-STORY ACCESSORY DWELLING UNIT TO THE (E) GARAGE PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Current Status
- CofO Issued on 3/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | COLIN LOREDO |
| Corrections Issued | 9/29/2020 | COLIN LOREDO |
| Quality Review Completed | 10/15/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/22/2020 | APPLICANT |
| Applicant returned to address corrections | 1/6/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 5/4/2021 | COLIN LOREDO |
| Plan Check Approved | 5/13/2021 | COLIN LOREDO |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 3/21/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/28/2023 | DEROLD HAUFF |
| CofO Issued | 3/28/2023 | DEROLD HAUFF |
| Permit Finaled | 3/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/6/2021 | WALLIE JONG |
| Construction within easement | Cleared | 3/5/2021 | RIDWAN HARDY |
| ZI | Cleared | 4/6/2021 | PABLO ESTRADA |
| Low Impact Development | Cleared | 4/26/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/28/2021 | WALLIE JONG |
Contact Information
| Contractor | Lorenzo Design Group Inc; Lic. No.: 530201-B | 3196 WILD HORSE CT THOUSAND OAKS, CA 91360 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/20/2021 | No Access for Inspection | ELMER BLAND |
| Pre-Inspection | 7/21/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/25/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 9/9/2021 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 10/4/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 10/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 10/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 11/19/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/2/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/2/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/13/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/13/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/22/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/5/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Sewer | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 3/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 3/9/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 3/9/2022 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/4/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/22/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 4/22/2022 | Approved | CHARLES BOGHOSKHAN |
| Gas Test | 7/25/2022 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Pre-Inspection | 7/28/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 11/18/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/18/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/18/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 1/17/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Test | 1/17/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/17/2023 | No Access for Inspection | OSVALDO PARAMO |
| Green Building Final | 2/17/2023 | No Access for Inspection | OSVALDO PARAMO |
| Final | 2/24/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 2/24/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 3/9/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 3/9/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 3/21/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |