7809 N GENESTA AVE 91406

Certificate Information: 7809 N GENESTA AVE 91406

Application / Permit
20010-20000-02941
Plan Check / Job No.
B20VN11391
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 27'-0" X 50'-6" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER ENGINEER
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/11/2020 JEROME MAGAT PALMA
Corrections Issued 9/11/2020 JEROME MAGAT PALMA
Plan Check Approved 1/12/2021 JEROME MAGAT PALMA
Issued 3/3/2021 APPLICANT
CofO in Progress 9/23/2022 RAUL OLAGI
CofO Issued 10/22/2022 MICHAEL SMITH
Permit Finaled 10/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/16/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/17/2020 GABRIEL ROBLES
Sewer availability Cleared 9/17/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/9/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/31/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/4/2021 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/26/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 4/5/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 4/5/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/18/2021 Partial Inspection JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 8/18/2021 Approved JACK KARGODORIAN
Sewer 8/18/2021 Approved JACK KARGODORIAN
Special/Order Compliance 10/19/2021 Corrections Issued RAUL OLAGI
Underground Mechanical 10/19/2021 Approved RAUL OLAGI
Underground Mechanical 11/15/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 2/3/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 2/3/2022 Partial Approval RAUL OLAGI
Insulation 2/22/2022 Approved RAUL OLAGI
Special/Order Compliance 2/22/2022 Corrections Issued RAUL OLAGI
Drywall Nailing 3/30/2022 Approved ALAN MORELOS
Shower Pan 3/30/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 4/5/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 9/9/2022 Approved RAUL OLAGI
ELECTRICAL-Final 9/9/2022 Corrections Issued RAUL OLAGI
Final 9/9/2022 Corrections Issued RAUL OLAGI
Green Building Final 9/9/2022 Approved RAUL OLAGI
Green Building Rough 9/9/2022 Approved RAUL OLAGI
HVAC-Final 9/9/2022 Approved RAUL OLAGI
PLUMBING-Final 9/9/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Approved RAUL OLAGI
Service/Power Release 9/9/2022 Corrections Issued RAUL OLAGI
Smoke Detectors 9/9/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 9/9/2022 Approved RAUL OLAGI
ELECTRICAL-Final 9/23/2022 Approved RAUL OLAGI
Final 9/23/2022 OK to Issue CofO RAUL OLAGI
PLUMBING-Final 9/23/2022 Approved RAUL OLAGI
Service/Power Release 9/23/2022 Approved RAUL OLAGI