7809 N GENESTA AVE 91406
Certificate Information: 7809 N GENESTA AVE 91406
- Application / Permit
- 20010-20000-02941
- Plan Check / Job No.
- B20VN11391
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 27'-0" X 50'-6" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER ENGINEER
- Permit Issued
- Issued on 3/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 9/11/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/12/2021 | JEROME MAGAT PALMA |
| Issued | 3/3/2021 | APPLICANT |
| CofO in Progress | 9/23/2022 | RAUL OLAGI |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/17/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/9/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/31/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/4/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/26/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/18/2021 | Partial Inspection | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 8/18/2021 | Approved | JACK KARGODORIAN |
| Sewer | 8/18/2021 | Approved | JACK KARGODORIAN |
| Special/Order Compliance | 10/19/2021 | Corrections Issued | RAUL OLAGI |
| Underground Mechanical | 10/19/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 11/15/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/3/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/3/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 2/22/2022 | Approved | RAUL OLAGI |
| Special/Order Compliance | 2/22/2022 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 3/30/2022 | Approved | ALAN MORELOS |
| Shower Pan | 3/30/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 4/5/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| Final | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/9/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 9/9/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 9/9/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 9/9/2022 | SGSOV Approved | RAUL OLAGI |
| Service/Power Release | 9/9/2022 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 9/9/2022 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 9/9/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 9/23/2022 | Approved | RAUL OLAGI |
| Final | 9/23/2022 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 9/23/2022 | Approved | RAUL OLAGI |
| Service/Power Release | 9/23/2022 | Approved | RAUL OLAGI |