16657 W BERMUDA ST 91344

Certificate Information: 16657 W BERMUDA ST 91344

Application / Permit
20010-20000-02931
Plan Check / Job No.
B20VN11285
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (23'-3"x 38'-0") IRR SHAPE 2-STORY DETACHED ACCESSORY DWELLING UNIT WITH ATT. TWO CAR GARAGE PER LAMC 12.22 A.33(c) and (d) . WORK PER ENGINEER.
Permit Issued
Issued on 9/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 TROY DEGUZMAN
Corrections Issued 9/25/2020 TROY DEGUZMAN
Quality Review Completed 9/28/2020 CHON CHIO KUO
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 4/19/2022 TROY DEGUZMAN
Plan Check Approved 8/30/2022 SELLA BENYAMIN
Issued 9/1/2022 APPLICANT
CofO in Progress 4/26/2023 JAVIER RAMOS JR
Permit Finaled 4/26/2023 MICHAEL SMITH
CofO Issued 4/26/2023 MICHAEL SMITH
Permit Finaled 4/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/16/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/16/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 1/6/2021 MARTIN FRAGOSO
Hydrant and Access approval Cleared 2/23/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 2/23/2021 JOHN TRIANTAFYLLOS
Construction within easement Cleared 8/30/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2022 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 10/19/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 10/19/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/29/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 11/29/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Corrections Issued JAVIER RAMOS JR
Green Building Rough 11/29/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 11/29/2022 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 11/29/2022 Corrections Issued JAVIER RAMOS JR
Verify Sprinkler Sign Off 11/29/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 11/30/2022 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 12/19/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 12/19/2022 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/19/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/19/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 12/19/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/19/2022 Approved JAVIER RAMOS JR
Underground Mechanical 12/19/2022 Partial Approval JAVIER RAMOS JR
Insulation 12/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/28/2022 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/4/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 1/4/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 1/4/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 1/4/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 1/9/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 1/23/2023 Approved JAVIER RAMOS JR
Shower Pan 1/23/2023 Approved JAVIER RAMOS JR
Sewer 3/8/2023 Approved JAVIER RAMOS JR
Underground Mechanical 3/8/2023 Approved JAVIER RAMOS JR
Final 4/5/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Approved JAVIER RAMOS JR
Green Building Final 4/5/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 4/5/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 4/5/2023 Approved JAVIER RAMOS JR
Pre-Inspection 4/11/2023 Approved JAVIER RAMOS JR
Service/Power Release 4/11/2023 Partial Inspection JAVIER RAMOS JR
Final 4/26/2023 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 4/26/2023 Approved JAVIER RAMOS JR