11849 W ARCHWOOD ST 91606
Certificate Information: 11849 W ARCHWOOD ST 91606
- Application / Permit
- 20010-20000-02922
- Plan Check / Job No.
- B20VN11259
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 31'9" DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33(C)(D) , ALL WORK PER WFPP The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Current Status
- Issued on 5/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2020 | RARES BODEA |
| Corrections Issued | 9/8/2020 | RARES BODEA |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
| Applicant returned to address corrections | 4/13/2022 | RARES BODEA |
| Plan Check Approved | 4/21/2022 | RARES BODEA |
| Issued | 5/14/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/5/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/5/2022 | CARLOS AGUILERA |
| Hold | Cleared | 2/10/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/25/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 3/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 4/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/8/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 12/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 12/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 12/3/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 12/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 2/17/2026 | Corrections Issued | MICHAEL CORTEZ |
| Shower Pan | 2/20/2026 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 3/10/2026 | Approved | GAREN HAYRAPETYAN |