8601 N AQUEDUCT AVE 91343

Certificate Information: 8601 N AQUEDUCT AVE 91343

Application / Permit
20010-20000-02915
Plan Check / Job No.
B20VN11188
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/9/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 COLIN LOREDO
Corrections Issued 10/26/2020 COLIN LOREDO
Quality Review Completed 10/26/2020 OMID HEDAYAT
Building Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 12/31/2020 COLIN LOREDO
Plan Check Approved 4/6/2021 JEFFREY TANGONAN
Issued 4/9/2021 APPLICANT
CofO in Progress 8/2/2023 RAUL OLAGI
CofO Issued 9/11/2023 RUBEN SALAS
Permit Finaled 9/11/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/10/2020 ABDULLAH SADOZAI
Hydrant and Access approval Cleared 12/18/2020 ROBERT DUFF
Low Impact Development Cleared 2/22/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/8/2021 GABRIEL ROBLES

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 5/6/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 5/28/2021 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 5/28/2021 Partial Approval ARTHUR SARGSYAN
Deputy Wood Construction 6/2/2021 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Approved ARTHUR SARGSYAN
Green Building Rough 6/11/2021 Approved ARTHUR SARGSYAN
Insulation 6/11/2021 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 6/11/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 6/17/2021 Not Ready for Inspection JACK KARGODORIAN
Insulation 6/17/2021 Approved JACK KARGODORIAN
Drywall Nailing 6/23/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/23/2021 Partial Approval JACK KARGODORIAN
Final 8/25/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 8/25/2021 Approved MICHAEL TEMPLE
Green Building Final 8/25/2021 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Not Required MICHAEL TEMPLE
Smoke Detectors 8/25/2021 Approved MICHAEL TEMPLE
Final 10/28/2021 Corrections Issued RAUL OLAGI
Final 8/1/2023 OK to Issue CofO RAUL OLAGI