6454 W FOOTHILL BLVD 91042

Certificate Information: 6454 W FOOTHILL BLVD 91042

Application / Permit
20010-20000-02913
Plan Check / Job No.
B20VN11187
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(9) Gas Station
Work Description
NEW GAS CANOPY STRUCTURE. 2 OF 2
Permit Issued
Issued on 3/17/2023
Issuing Office
Valley
Current Status
CofO in Progress on 8/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 CHON CHIO KUO
Corrections Issued 10/7/2020 CHON CHIO KUO
Quality Review Completed 10/14/2020 STEVEN KIM
Building Plans Picked Up 10/16/2020 APPLICANT
Disabled Access Plans Picked Up 11/2/2020 APPLICANT
Green Plans Picked Up 11/2/2020 APPLICANT
Plan Check Approved 3/17/2023 RAPHAEL ROSAS
Issued 3/17/2023 APPLICANT
CofO in Progress 8/16/2024 DANNY RODRIGUEZ

Permit Application Clearance Information

Green Code Cleared 3/16/2021 MICHAEL AYERS
Highway dedication Cleared 12/9/2021 DAGOVERTO GUERRERO
Permit Cleared 12/9/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 3/2/2022 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/31/2022 CARLOS AGUILERA
Driveway location Cleared 6/16/2022 BRANDON WILSON
Driveway location Cleared 6/16/2022 BRANDON WILSON
Eng Process Fee Ord 176,300 Cleared 6/16/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/16/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 6/22/2022 ERIC FRENCH
DAS Clearance Cleared 10/28/2022 CHON CHIO KUO
Comm Cor/Mini-Mall Cleared 11/30/2022 RYAN LY
Comm Cor/Mini-Mall Cleared 11/30/2022 RYAN LY
Comm Cor/Mini-Mall Cleared 11/30/2022 RYAN LY
Prkng lot landscape/Water mgmt Cleared 11/30/2022 RYAN LY
Specific Plan Cleared 11/30/2022 RYAN LY
ZA Case Cleared 11/30/2022 RYAN LY
ZI Cleared 11/30/2022 RYAN LY
GPI Written Notices Cleared 1/10/2023 CHON CHIO KUO
Grading Pre-Inspection Cleared 1/10/2023 CHON CHIO KUO
Work Adjacent to Public Way Cleared 1/27/2023 LEE GUILBEAUX

Contact Information

Contractor Ortiz & Son Inc; Lic. No.: 429887-B 7161 MCNEIL LANE      BUENA PARK, CA 90620
Engineer Ghaderi,, Nader; Lic. No.: C36475 28405 SAND CANYON ROAD STE B      CANYON COUNTRY, CA 91387
Engineer Rastegari,, Esmail Nader; Lic. No.: C43332 1150 E ORANGETHORPE 108      PLACENTIA, CA 92870

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/24/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/27/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/28/2023 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 5/11/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/1/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/2/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/9/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 8/15/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 8/18/2023 Conditional Approval DANNY RODRIGUEZ
Final 7/31/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/31/2024 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV No Gas DANNY RODRIGUEZ
Smoke Detectors 7/31/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/31/2024 Approved DANNY RODRIGUEZ
Wood Frame 7/31/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 8/5/2024 OK to Issue CofO DANNY RODRIGUEZ
Footing/Foundation/Slab 8/5/2024 Approved DANNY RODRIGUEZ
Smoke Detectors 8/5/2024 Approved DANNY RODRIGUEZ
Structural Steel Frame 8/5/2024 Approved DANNY RODRIGUEZ