6454 W FOOTHILL BLVD 91042
Certificate Information: 6454 W FOOTHILL BLVD 91042
- Application / Permit
- 20010-20000-02913
- Plan Check / Job No.
- B20VN11187
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (9) Gas Station
- Work Description
- NEW GAS CANOPY STRUCTURE. 2 OF 2
- Permit Issued
- Issued on 3/17/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 8/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | CHON CHIO KUO |
| Corrections Issued | 10/7/2020 | CHON CHIO KUO |
| Quality Review Completed | 10/14/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/16/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/2/2020 | APPLICANT |
| Green Plans Picked Up | 11/2/2020 | APPLICANT |
| Plan Check Approved | 3/17/2023 | RAPHAEL ROSAS |
| Issued | 3/17/2023 | APPLICANT |
| CofO in Progress | 8/16/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| Green Code | Cleared | 3/16/2021 | MICHAEL AYERS |
| Highway dedication | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
| Permit | Cleared | 12/9/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/2/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | CARLOS AGUILERA |
| Driveway location | Cleared | 6/16/2022 | BRANDON WILSON |
| Driveway location | Cleared | 6/16/2022 | BRANDON WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/16/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 6/22/2022 | ERIC FRENCH |
| DAS Clearance | Cleared | 10/28/2022 | CHON CHIO KUO |
| Comm Cor/Mini-Mall | Cleared | 11/30/2022 | RYAN LY |
| Comm Cor/Mini-Mall | Cleared | 11/30/2022 | RYAN LY |
| Comm Cor/Mini-Mall | Cleared | 11/30/2022 | RYAN LY |
| Prkng lot landscape/Water mgmt | Cleared | 11/30/2022 | RYAN LY |
| Specific Plan | Cleared | 11/30/2022 | RYAN LY |
| ZA Case | Cleared | 11/30/2022 | RYAN LY |
| ZI | Cleared | 11/30/2022 | RYAN LY |
| GPI Written Notices | Cleared | 1/10/2023 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 1/10/2023 | CHON CHIO KUO |
| Work Adjacent to Public Way | Cleared | 1/27/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Ortiz & Son Inc; Lic. No.: 429887-B | 7161 MCNEIL LANE BUENA PARK, CA 90620 |
| Engineer | Ghaderi,, Nader; Lic. No.: C36475 | 28405 SAND CANYON ROAD STE B CANYON COUNTRY, CA 91387 |
| Engineer | Rastegari,, Esmail Nader; Lic. No.: C43332 | 1150 E ORANGETHORPE 108 PLACENTIA, CA 92870 |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/24/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 4/27/2023 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 4/28/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Special/Order Compliance | 5/11/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 8/1/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 8/2/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 8/9/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Steel/Welding | 8/15/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 8/18/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Final | 7/31/2024 | No Access for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 7/31/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV No Gas | DANNY RODRIGUEZ |
| Smoke Detectors | 7/31/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Verify Sprinkler Sign Off | 7/31/2024 | Approved | DANNY RODRIGUEZ |
| Wood Frame | 7/31/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 8/5/2024 | OK to Issue CofO | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 8/5/2024 | Approved | DANNY RODRIGUEZ |
| Smoke Detectors | 8/5/2024 | Approved | DANNY RODRIGUEZ |
| Structural Steel Frame | 8/5/2024 | Approved | DANNY RODRIGUEZ |