10706 W KESWICK ST 91352

Certificate Information: 10706 W KESWICK ST 91352

Application / Permit
20010-20000-02907
Plan Check / Job No.
B20VN11162
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 25'-6" X 30'-1" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SELLA BENYAMIN
Corrections Issued 9/21/2020 SELLA BENYAMIN
Building Plans Picked Up 9/23/2020 APPLICANT
Plan Check Approved 10/1/2021 SELLA BENYAMIN
Issued 10/12/2021 APPLICANT
CofO in Progress 2/24/2023 MATTHEW NELSON
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 12/11/2020 RIDWAN HARDY
Low Impact Development Cleared 5/9/2021 JORGE MEJIA LEMUS
Address approval Cleared 5/20/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/20/2021 CARLOS AGUILERA
Sewer availability Cleared 5/26/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 9/16/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 9/21/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/16/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 12/16/2021 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 12/16/2021 Partial Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 12/27/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 1/4/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/25/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Sewer 2/25/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 2/25/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/9/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/9/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 3/9/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 3/9/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 3/9/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 3/22/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/29/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/29/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 5/6/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/1/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 7/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 7/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/25/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 7/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 7/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 7/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 7/25/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 7/25/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 8/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 8/31/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 8/31/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 8/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 8/31/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 10/5/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 10/5/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Service/Power Release 10/5/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 2/16/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 2/16/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 2/16/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 2/22/2023 Not Ready for Inspection MATTHEW NELSON
Green Building Final 2/22/2023 Partial Inspection MATTHEW NELSON
Service/Power Release 2/22/2023 Not Ready for Inspection MATTHEW NELSON
Final 2/24/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 2/24/2023 Approved MATTHEW NELSON
Service/Power Release 2/24/2023 Approved MATTHEW NELSON