8151 N HAZELTINE AVE 91402
Certificate Information: 8151 N HAZELTINE AVE 91402
- Application / Permit
- 20010-20000-02905
- Plan Check / Job No.
- B20VN11148
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 24'-1"X 20'-0" IRREGULAR SHAPE DETACH. ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. SEE COMMENT.
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 11/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2020 | PARISA ZAHABI |
| Corrections Issued | 9/19/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 11/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 12/30/2020 | PARISA ZAHABI |
| Plan Check Approved | 2/17/2021 | PARISA ZAHABI |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 10/20/2021 | GREGG CUMMINGS |
| CofO Issued | 11/13/2021 | MICHAEL SMITH |
| Permit Finaled | 11/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 10/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 11/27/2020 | PARISA ZAHABI |
| Sewer availability | Cleared | 12/14/2020 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 2/6/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 4/19/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/4/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/4/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 5/4/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 6/7/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/7/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 6/7/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/14/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/14/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/14/2021 | Approved | GREGG CUMMINGS |
| Insulation | 6/21/2021 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/21/2021 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 6/30/2021 | Approved | GREGG CUMMINGS |
| Insulation | 6/30/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/20/2021 | Approved | ALAN MORELOS |
| Shower Pan | 7/20/2021 | Approved | ALAN MORELOS |
| Final | 9/13/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/13/2021 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 9/13/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/13/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/19/2021 | Approved | GREGG CUMMINGS |
| Final | 10/19/2021 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 10/19/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 10/19/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/19/2021 | Approved | GREGG CUMMINGS |
| Service/Power Release | 10/19/2021 | Approved | GREGG CUMMINGS |