14904 W GREENLEAF ST 91403
Certificate Information: 14904 W GREENLEAF ST 91403
- Application / Permit
- 20010-20000-02898
- Plan Check / Job No.
- B20VN11133
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/7/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/23/2020 | SELLA BENYAMIN |
| Quality Review Completed | 9/25/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/1/2020 | APPLICANT |
| Applicant returned to address corrections | 8/24/2021 | SELLA BENYAMIN |
| Plan Check Approved | 9/14/2021 | SELLA BENYAMIN |
| Issued | 10/7/2021 | APPLICANT |
| CofO in Progress | 10/13/2022 | THOMAS FINNILA |
| Permit Finaled | 11/3/2022 | MICHAEL SMITH |
| CofO Issued | 11/3/2022 | MICHAEL SMITH |
| Permit Finaled | 11/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/1/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/28/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/4/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | MARKOS PEREZ-BRAN |
| Miscellaneous | Cleared | 7/28/2021 | MARKOS PEREZ-BRAN |
| Permit | Cleared | 7/28/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 7/29/2021 | MARKOS PEREZ-BRAN |
| Trees in Parkway | Cleared | 8/11/2021 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 11/4/2021 | Corrections Issued | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 11/5/2021 | Approved | JACK KARGODORIAN |
| Piling/Pier/Caisson | 11/8/2021 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 11/16/2021 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 12/3/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 12/6/2021 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/19/2022 | Approved | JACK KARGODORIAN |
| Shower Pan | 1/21/2022 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 1/27/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/7/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 2/7/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/8/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 2/8/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/17/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 2/17/2022 | Approved | JACK KARGODORIAN |
| Insulation | 2/25/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/8/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/29/2022 | Approved | ROBERT GOLD |
| PLUMBING-Final | 8/29/2022 | Approved | ROBERT GOLD |
| Gas Test | 9/6/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/6/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 10/3/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 10/3/2022 | Approved | JACK KARGODORIAN |
| HVAC-Final | 10/3/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 10/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 10/3/2022 | Approved | JACK KARGODORIAN |
| Final | 10/11/2022 | Corrections Issued | THOMAS FINNILA |
| Service/Power Release | 10/11/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 10/13/2022 | OK to Issue CofO | THOMAS FINNILA |
| Service/Power Release | 10/13/2022 | Approved | THOMAS FINNILA |