12516 W VOSE ST 91605
Certificate Information: 12516 W VOSE ST 91605
- Application / Permit
- 20010-20000-02896
- Plan Check / Job No.
- B20VN11123
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 38' X 24' ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 9/3/2020 | SEWADA ZADOORIAN MILAGARDI |
| Building Plans Picked Up | 9/14/2020 | APPLICANT |
| Plan Check Approved | 1/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 9/29/2021 | MICHAEL PELHAM |
| Permit Finaled | 10/12/2021 | MICHAEL SMITH |
| CofO Issued | 10/12/2021 | MICHAEL SMITH |
| Permit Finaled | 10/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 10/7/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 11/12/2020 | ROBIN YAMADA |
| Miscellaneous | Cleared | 11/20/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 11/20/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/20/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 12/14/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/14/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2021 | Approved | BRENDAN LOONEY |
| Sewer | 3/15/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/18/2021 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 3/23/2021 | Approved | DANIEL DREW |
| Sewer | 4/20/2021 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/7/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 5/24/2021 | Approved | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 5/24/2021 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 5/26/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 6/1/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/1/2021 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 6/1/2021 | Approved | RICHARD DOCKUS |
| Insulation | 6/14/2021 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 6/22/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/22/2021 | Approved | RICHARD DOCKUS |
| Gas Test | 7/2/2021 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 7/2/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/18/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/18/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/18/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/26/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 9/2/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/2/2021 | Approved | CHRISTOPHE COCHRAN |