- NEW 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/25/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/9/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Plan Check Approved | 9/13/2021 | JON BLAINE |
| Issued | 10/4/2021 | APPLICANT |
| CofO in Progress | 3/8/2024 | RAUL OLAGI |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
| CofO Issued | 4/10/2024 | RUBEN SALAS |
| Permit Finaled | 4/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 3/4/2021 | MITESH PATEL |
| Construction near power lines | Cleared | 3/10/2021 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 3/26/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Inspection | RAUL OLAGI |
| PLUMBING-Rough | 11/2/2022 | Partial Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 11/15/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/17/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Off-Hour Fees Due | |
| Final | 11/17/2022 | Off-Hour Fees Due | |
| Green Building Final | 11/17/2022 | Off-Hour Fees Due | |
| Green Building Rough | 11/17/2022 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | Off-Hour Fees Due | |
| Service/Power Release | 11/17/2022 | Off-Hour Fees Due | |
| Smoke Detectors | 11/17/2022 | Off-Hour Fees Due | |
| Verify Sprinkler Sign Off | 11/17/2022 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 2/16/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 2/21/2023 | Approved | RAUL OLAGI |
| Green Building Rough | 2/21/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/21/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/21/2023 | Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 2/21/2023 | Approved | RAUL OLAGI |
| Insulation | 4/13/2023 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 4/13/2023 | Approved | RAUL OLAGI |
| Shower Pan | 4/13/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 4/25/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 7/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 7/11/2023 | Approved | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Not Ready | RAUL OLAGI |
| ELECTRICAL-Final | 1/9/2024 | Corrections Issued | RAUL OLAGI |
| Final | 1/9/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 1/9/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 1/9/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 1/24/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/24/2024 | Approved | RAUL OLAGI |
| Green Building Final | 1/24/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 1/24/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/24/2024 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/24/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 3/7/2024 | Approved | RAUL OLAGI |
| Final | 3/7/2024 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 3/7/2024 | Approved | RAUL OLAGI |