Underground Mechanical
|
9/3/2021
|
Conditional Approval
|
SCOTT FINNILA
|
|
Footing/Foundation/Slab
|
11/2/2021
|
Corrections Issued
|
SCOTT FINNILA
|
|
METHANE-Barrier
|
11/2/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
METHANE-Subgrade
|
11/2/2021
|
Partial Inspection
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
11/4/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
METHANE-Barrier
|
11/16/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
METHANE-Rough
|
11/16/2021
|
Not Ready for Inspection
|
SCOTT FINNILA
|
|
METHANE-Subgrade
|
11/16/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
METHANE-Subgrade
|
11/17/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Methane Barrier
|
11/19/2021
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Reinf. Concrete
|
11/22/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Deputy Reinf. Concrete
|
11/23/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
11/23/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Barrier
|
11/23/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
12/15/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
12/16/2021
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
12/22/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
12/23/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Sewer
|
1/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
1/6/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/2/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
2/3/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
2/7/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/8/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/10/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/17/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/18/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/25/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/28/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
3/2/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/4/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Deputy Wood Construction
|
3/7/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/8/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/9/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/10/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
3/10/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
3/11/2022
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
3/15/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/16/2022
|
Partial Approval
|
SCOTT FINNILA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/17/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/29/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/31/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
4/1/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
4/4/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
4/5/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
4/7/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/13/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/26/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
4/28/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
4/29/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2022
|
Corrections Issued
|
STUART CHAPMAN
|
|
PLUMBING-Rough
|
5/6/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Verify Rec and Parks Fee Memo
|
5/13/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
5/16/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/7/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/12/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
7/15/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
7/15/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
7/20/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
7/22/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
7/22/2022
|
Corrections Issued
|
SCOTT FINNILA
|
|
HVAC-Rough
|
8/1/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/3/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/8/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Rough
|
8/8/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Deputy Wood Construction
|
8/16/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
8/17/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Green Building Rough
|
8/17/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
8/17/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Verify Sprinkler Sign Off
|
8/17/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
8/18/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Rough
|
8/19/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Insulation
|
8/19/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Rough
|
8/19/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Shower Pan
|
8/26/2022
|
Approved
|
STUART CHAPMAN
|
|
Drywall Nailing
|
8/30/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
|
Interior/Exterior Lathing
|
9/23/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
11/18/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
12/2/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
12/2/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
12/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
12/8/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
12/14/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
12/21/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
12/29/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Final
|
1/13/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Service/Power Release
|
1/13/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
PLUMBING-Final
|
2/6/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
2/16/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
ELECTRICAL-Final
|
2/17/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Gas Test
|
2/17/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
HVAC-Final
|
2/17/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
3/24/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Drywall Nailing
|
6/1/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Green Building Final
|
6/1/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Final
|
6/1/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
SGSOV-Seismic Gas S/O Valve
|
6/1/2023
|
SGSOV Approved
|
ALEJANDRO DE ARTOLA
|
|
Smoke Detectors
|
6/1/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
BUILDING-Rough-Frame
|
6/2/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Final
|
6/2/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Footing/Foundation/Slab
|
6/2/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Rough
|
6/2/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
METHANE-Subgrade
|
6/2/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Structural Steel Frame
|
6/2/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Special/Order Compliance
|
6/8/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Final
|
6/9/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
|
Final
|
7/7/2023
|
OK to Issue CofO
|
ALEJANDRO DE ARTOLA
|