14410 W FILMORE ST 91331
Certificate Information: 14410 W FILMORE ST 91331
- Application / Permit
- 20010-20000-02844
- Plan Check / Job No.
- B20VN10927
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (35'-0"x 41'-6") DETACHED ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)and(d). WORK PER ENGINEER.
- Permit Issued
- Issued on 11/19/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | TROY DEGUZMAN |
| Corrections Issued | 8/26/2020 | TROY DEGUZMAN |
| Building Plans Picked Up | 8/27/2020 | APPLICANT |
| Plan Check Approved | 11/19/2020 | TROY DEGUZMAN |
| Issued | 11/19/2020 | APPLICANT |
| CofO in Progress | 8/4/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
| CofO Issued | 9/25/2021 | MICHAEL SMITH |
| Permit Finaled | 9/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 10/3/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/6/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/4/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/9/2020 | MATTHEW CRAIG |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: C26491 | 1323 N NIAGARA STREET BURBANK, CA 91505 |
| Contractor | Owner-Builder | , |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/25/2020 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/18/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 12/21/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/8/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 1/8/2021 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 1/8/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/12/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/12/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/12/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/12/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/14/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 1/15/2021 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 1/15/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/20/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/21/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/21/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/21/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/21/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/21/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 4/21/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| Final | 4/30/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/30/2021 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/30/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/5/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 8/5/2021 | Approved | JENNIFER RABUCHIN |