1319 W 65TH PL 90044

Certificate Information: 1319 W 65TH PL 90044

Application / Permit
20010-20000-02843
Plan Check / Job No.
B20VN10923
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'-6" X 32'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP.
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 6/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 JENNIFER LEE
Corrections Issued 9/9/2020 JENNIFER LEE
Plan Check Approved 2/25/2021 JENNIFER LEE
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/4/2021 APPLICANT
CofO in Progress 6/16/2023 ENRIQUE MIRELES
CofO in Progress 6/16/2023 ENRIQUE MIRELES
Permit Finaled 6/18/2023 DEROLD HAUFF
CofO Issued 6/18/2023 DEROLD HAUFF
Permit Finaled 6/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 12/8/2020 JORGE MEJIA LEMUS
Hydrant and Access approval Cleared 12/21/2020 MATTHEW CRAIG
Address approval Cleared 1/4/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/5/2021 JEANIE LAM
Sewer availability Cleared 1/5/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 1/20/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/27/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 5/27/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 6/16/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/27/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/27/2021 Approved FREDDIE RIVERA
Green Building Rough 9/27/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 9/27/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/27/2021 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 9/27/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/29/2021 Approved FREDDIE RIVERA
Green Building Rough 9/29/2021 Approved FREDDIE RIVERA
HVAC-Rough 9/29/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/29/2021 Approved FREDDIE RIVERA
Wood Frame 9/29/2021 Approved FREDDIE RIVERA
Insulation 10/14/2021 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 10/19/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/19/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/7/2022 Approved ENRIQUE MIRELES
Final 9/7/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 9/7/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/7/2022 Approved ENRIQUE MIRELES
Final 9/14/2022 Corrections Issued RYAN SALAZAR
Service/Power Release 9/14/2022 Not Ready for Inspection RYAN SALAZAR
Final 9/21/2022 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 9/21/2022 Approved ENRIQUE MIRELES