1319 W 65TH PL 90044
Certificate Information: 1319 W 65TH PL 90044
- Application / Permit
- 20010-20000-02843
- Plan Check / Job No.
- B20VN10923
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'-6" X 32'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/3/2021
- Issuing Office
- Current Status
- CofO Issued on 6/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | JENNIFER LEE |
| Corrections Issued | 9/9/2020 | JENNIFER LEE |
| Plan Check Approved | 2/25/2021 | JENNIFER LEE |
| Issued | 3/3/2021 | APPLICANT |
| Building Plans Picked Up | 3/4/2021 | APPLICANT |
| CofO in Progress | 6/16/2023 | ENRIQUE MIRELES |
| CofO in Progress | 6/16/2023 | ENRIQUE MIRELES |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
| CofO Issued | 6/18/2023 | DEROLD HAUFF |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/8/2020 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 12/21/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 1/4/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | JEANIE LAM |
| Sewer availability | Cleared | 1/5/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 1/20/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/25/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/16/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/27/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 9/27/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/27/2021 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/27/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/29/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/29/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/29/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 9/29/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 9/29/2021 | Approved | FREDDIE RIVERA |
| Insulation | 10/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 10/19/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/19/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/7/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/7/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/7/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/14/2022 | Corrections Issued | RYAN SALAZAR |
| Service/Power Release | 9/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 9/21/2022 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 9/21/2022 | Approved | ENRIQUE MIRELES |