9981 N TAMARACK AVE 91331
Certificate Information: 9981 N TAMARACK AVE 91331
- Application / Permit
- 20010-20000-02842
- Plan Check / Job No.
- B20VN10920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (19'-8"x 28'-8") TWO-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | TROY DEGUZMAN |
| Corrections Issued | 9/18/2020 | TROY DEGUZMAN |
| Quality Review Completed | 9/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Applicant returned to address corrections | 11/20/2020 | TROY DEGUZMAN |
| Plan Check Approved | 1/20/2022 | TROY DEGUZMAN |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 4/20/2023 | MICHEL ABAJAN |
| CofO Issued | 4/25/2023 | RONALD MYRICK |
| Permit Finaled | 4/25/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/3/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 1/11/2021 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 2/10/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/21/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2022 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 2/14/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 2/14/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/16/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/24/2022 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 3/24/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 6/23/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/6/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/6/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 7/6/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 7/6/2022 | Approved | MISAEL ESPARZA |
| METHANE-Rough | 7/6/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 7/6/2022 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 7/6/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/11/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/11/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/11/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/19/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/19/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/26/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/26/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/18/2023 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 2/2/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/14/2023 | Approved | MICHEL ABAJAN |
| Final | 3/14/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/14/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/14/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/14/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 3/14/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/14/2023 | Approved | MICHEL ABAJAN |
| Final | 3/20/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 3/20/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 4/20/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 4/20/2023 | Approved | MICHEL ABAJAN |