11700 W ERWIN ST 91606

Certificate Information: 11700 W ERWIN ST 91606

Application / Permit
20010-20000-02841
Plan Check / Job No.
B20VN10905
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ENG'R DESIGN
Permit Issued
Issued on 5/17/2022
Issuing Office
Current Status
CofO Issued on 10/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 NILOOFAR MEHRAIN
Corrections Issued 9/1/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/4/2020 APPLICANT
Plan Check Approved 5/11/2022 NILOOFAR MEHRAIN
Issued 5/17/2022 APPLICANT
CofO in Progress 8/3/2023 JOHN HAYES
CofO Issued 10/15/2024 DANIEL ORRANTE
Permit Finaled 10/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 9/2/2020 JASON SHEETS
Address approval Cleared 9/10/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/11/2020 ADRIAN CASTRO
Sewer availability Cleared 9/11/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 9/25/2021 GILBERT URREA
Construction near power lines Cleared 9/28/2021 RIDWAN HARDY
Construction within easement Cleared 9/28/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/26/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2022 Corrections Issued JOHN HAYES
Underground Mechanical 10/4/2022 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 10/18/2022 Corrections Issued ROBERT GOLD
PLUMBING-Rough 10/18/2022 Corrections Issued ROBERT GOLD
PLUMBING-Rough 10/24/2022 Conditional Approval THOMAS FINNILA
Underground Mechanical 10/24/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 10/31/2022 Partial Approval JOHN HAYES
Wood Frame 12/5/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/16/2023 Partial Approval JOHN HAYES
ELECTRICAL-Rough 2/16/2023 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/16/2023 Not Ready for Inspection JOHN HAYES
HVAC-Rough 2/16/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 2/16/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 2/16/2023 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/20/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 3/20/2023 Approved JOHN COLEMAN
Green Building Rough 3/20/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 3/20/2023 Approved JOHN COLEMAN
PLUMBING-Rough 3/20/2023 Corrections Issued JOHN COLEMAN
Verify Sprinkler Sign Off 3/20/2023 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 4/5/2023 Approved JOHN HAYES
Green Building Rough 4/5/2023 Approved JOHN HAYES
Interior/Exterior Lathing 4/5/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 4/5/2023 Approved JOHN HAYES
Verify Sprinkler Sign Off 4/5/2023 Approved JOHN HAYES
Insulation 4/11/2023 Approved JOHN HAYES
Drywall Nailing 4/14/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 5/15/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 5/19/2023 Corrections Issued JOHN HAYES
Interior/Exterior Lathing 5/26/2023 Approved DAVID MATSON
Final 7/18/2023 Corrections Issued JOHN HAYES
Final 7/27/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/27/2023 Approved JENNIFER RABUCHIN
Green Building Final 7/27/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 7/27/2023 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 7/27/2023 Approved JENNIFER RABUCHIN
Final 8/2/2023 OK to Issue CofO JOHN HAYES
Service/Power Release 8/2/2023 Approved JOHN HAYES