11700 W ERWIN ST 91606
Certificate Information: 11700 W ERWIN ST 91606
- Application / Permit
- 20010-20000-02841
- Plan Check / Job No.
- B20VN10905
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ENG'R DESIGN
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/1/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 9/4/2020 | APPLICANT |
| Plan Check Approved | 5/11/2022 | NILOOFAR MEHRAIN |
| Issued | 5/17/2022 | APPLICANT |
| CofO in Progress | 8/3/2023 | JOHN HAYES |
| CofO Issued | 10/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hold | Cleared | 9/2/2020 | JASON SHEETS |
| Address approval | Cleared | 9/10/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/11/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/25/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 9/28/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/28/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 4/26/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 10/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/18/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 10/18/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 10/24/2022 | Conditional Approval | THOMAS FINNILA |
| Underground Mechanical | 10/24/2022 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | JOHN HAYES |
| Wood Frame | 12/5/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/16/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 2/16/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/16/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/16/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/16/2023 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 2/16/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/20/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/20/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 3/20/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 3/20/2023 | Corrections Issued | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 3/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/5/2023 | Approved | JOHN HAYES |
| Green Building Rough | 4/5/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 4/5/2023 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 4/5/2023 | Approved | JOHN HAYES |
| Insulation | 4/11/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 4/14/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 5/15/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 5/19/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 5/26/2023 | Approved | DAVID MATSON |
| Final | 7/18/2023 | Corrections Issued | JOHN HAYES |
| Final | 7/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 7/27/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/2/2023 | OK to Issue CofO | JOHN HAYES |
| Service/Power Release | 8/2/2023 | Approved | JOHN HAYES |