12901 W ELANA LANE 91605

Certificate Information: 12901 W ELANA LANE 91605

Application / Permit
20010-20000-02838
Plan Check / Job No.
B20VN10885
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 50' X 40' TWO STORY SFD PER TENTATIVE TRACT TT-72966-M1 , NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/1/2022
Issuing Office
Current Status
Issued on 11/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 RARES BODEA
Corrections Issued 10/2/2020 RARES BODEA
Quality Review Completed 10/6/2020 STEVEN KIM
Building Plans Picked Up 10/8/2020 APPLICANT
Applicant returned to address corrections 5/13/2022 RARES BODEA
Plan Check Approved 11/1/2022 RARES BODEA
Issued 11/1/2022 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 10/21/2020 LEE GUILBEAUX
Permit Cleared 10/21/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/21/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/21/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/23/2020 LEE GUILBEAUX
Sewer availability Cleared 10/23/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 12/21/2020 MATTHEW CRAIG
"T" removal Cleared 6/3/2021 DANG NGUYEN
Miscellaneous Cleared 6/3/2021 DANG NGUYEN
Private street Cleared 6/3/2021 DANG NGUYEN
Tract Map conditions Cleared 6/3/2021 DANG NGUYEN
Frnt yard landscape/Water mgmt Cleared 9/1/2021 DANG NGUYEN
Address approval Cleared 3/14/2022 LEE GUILBEAUX
Trees in Parkway Cleared 4/19/2022 ADALBERTO VERA
Low Impact Development Cleared 10/28/2022 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/6/2022 Approved SEAN WIRCH
Footing/Foundation/Slab 12/6/2022 Approved SEAN WIRCH
Underground Mechanical 12/6/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/27/2023 Partial Approval SEAN WIRCH
Deputy Wood Construction 1/30/2023 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 3/10/2023 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/10/2023 Approved SEAN WIRCH
HVAC-Rough 3/10/2023 Approved SEAN WIRCH
PLUMBING-Rough 3/10/2023 Approved SEAN WIRCH
Drywall Nailing 4/6/2023 Approved SEAN WIRCH
Green Building Rough 4/6/2023 Approved SEAN WIRCH
Interior/Exterior Lathing 4/6/2023 Partial Approval SEAN WIRCH
Shower Pan 4/6/2023 Approved SEAN WIRCH
ELECTRICAL-Final 1/10/2024 Partial Approval SEAN WIRCH
HVAC-Final 1/10/2024 Not Ready for Inspection SEAN WIRCH
PLUMBING-Final 1/10/2024 Not Ready for Inspection SEAN WIRCH
Service/Power Release 1/10/2024 Approved SEAN WIRCH