16746 W BAHAMA ST 91343

Certificate Information: 16746 W BAHAMA ST 91343

Application / Permit
20010-20000-02825
Plan Check / Job No.
B20VN10811
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 47' 9" X 27' IRR.-SHAPE DETACHED 1-STORY ADU PER LAMC 12.22 A.33(C) AND (D). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 3/7/2021
Issuing Office
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/24/2020 GURUNATH NESARAJAH
Corrections Issued 8/25/2020 GURUNATH NESARAJAH
Plan Check Approved 3/6/2021 GURUNATH NESARAJAH
Issued 3/7/2021 APPLICANT
Building Plans Picked Up 3/10/2021 APPLICANT
CofO in Progress 9/16/2021 JACK KARGODORIAN
CofO Issued 11/30/2021 MICHAEL SMITH
Permit Finaled 11/30/2021 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 8/27/2020 STEVEN WECHSLER
Address approval Cleared 8/28/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/31/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 9/1/2020 ADRIAN CASTRO
Sewer availability Cleared 9/1/2020 ADRIAN CASTRO
Low Impact Development Cleared 2/25/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/25/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/11/2021 Partial Approval ARTHUR SARGSYAN
Pre-Inspection 3/11/2021 Approved ARTHUR SARGSYAN
Sewer 3/11/2021 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 3/15/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 4/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
Verify Sprinkler Sign Off 4/1/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 4/22/2021 Approved ARTHUR SARGSYAN
HVAC-Rough 4/22/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/22/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/29/2021 Approved ARTHUR SARGSYAN
Green Building Rough 4/29/2021 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 4/29/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/30/2021 Partial Approval STEVEN BACK
Insulation 5/3/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 5/11/2021 Approved ARTHUR SARGSYAN
Final 8/24/2021 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 8/24/2021 Approved MICHAEL TEMPLE
Green Building Final 8/24/2021 Not Ready for Inspection MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Approved MICHAEL TEMPLE
Service/Power Release 8/24/2021 Corrections Issued MICHAEL TEMPLE
Smoke Detectors 8/24/2021 Not Ready for Inspection MICHAEL TEMPLE
Final 8/31/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 8/31/2021 Approved JACK KARGODORIAN
Service/Power Release 8/31/2021 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 8/31/2021 Approved JACK KARGODORIAN
Final 9/7/2021 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 9/7/2021 Not Ready for Inspection JACK KARGODORIAN
Final 9/9/2021 Corrections Issued JACK KARGODORIAN
Service/Power Release 9/9/2021 Not Ready for Inspection JACK KARGODORIAN
Final 9/16/2021 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 9/16/2021 Approved JACK KARGODORIAN