14644 W ADDISON ST 91403

Certificate Information: 14644 W ADDISON ST 91403

Application / Permit
20010-20000-02821
Plan Check / Job No.
B20VN10765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 58'4" X 30' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE NFPA-13D FIRE SPRINKLERS REQUIRED , ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 RARES BODEA
Corrections Issued 9/21/2020 RARES BODEA
Quality Review Completed 9/24/2020 STEVEN KIM
Building Plans Picked Up 9/24/2020 APPLICANT
Applicant returned to address corrections 1/27/2021 RARES BODEA
Applicant returned to address corrections 5/25/2021 RARES BODEA
Applicant returned to address corrections 7/26/2021 RARES BODEA
Plan Check Approved 7/29/2021 RARES BODEA
Issued 7/30/2021 APPLICANT
CofO in Progress 3/31/2022 JACK KARGODORIAN
CofO Issued 4/19/2022 MICHAEL SMITH
Permit Finaled 4/19/2022 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 9/24/2020 MIGUEL GAMBOA
Address approval Cleared 10/2/2020 ADRIAN CASTRO
Permit Cleared 10/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/7/2020 ADRIAN CASTRO
Sewer availability Cleared 10/7/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/5/2021 KURT CORRAL
Trees in Parkway Cleared 3/31/2021 JOHN KIM
ZI Cleared 4/12/2021 MIGUEL GAMBOA
Low Impact Development Cleared 5/5/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/5/2021 GABRIEL ROBLES

Contact Information

Contractor Builder Hub Inc; Lic. No.: 976592-B 12501 SHERMAN WAY      NORTH HOLLYWOOD, CA 91605
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2021 Partial Inspection JOHN HAYES
PLUMBING-Rough 8/27/2021 Not Ready for Inspection CHARLES POWELL
Pre-Inspection 8/27/2021 Partial Inspection ALIZAH MAYAGOITIA
Sewer 8/27/2021 Approved CHARLES POWELL
Underground Mechanical 8/27/2021 Approved CHARLES POWELL
Excavation/Setback/Form/Re-Bar 9/2/2021 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 9/8/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 9/21/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 9/21/2021 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 10/4/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/4/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/4/2021 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 10/14/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval JACK KARGODORIAN
Green Building Rough 10/14/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 10/20/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 10/20/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 10/25/2021 Corrections Issued JACK KARGODORIAN
Green Building Rough 10/25/2021 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 10/25/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 11/2/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/3/2021 Corrections Issued JACK KARGODORIAN
Green Building Rough 11/3/2021 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 11/3/2021 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/9/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 11/9/2021 Partial Approval JACK KARGODORIAN
Shower Pan 11/9/2021 Not Ready for Inspection JACK KARGODORIAN
Verify Sprinkler Sign Off 11/9/2021 Approved JACK KARGODORIAN
Insulation 11/12/2021 Approved JACK KARGODORIAN
Shower Pan 11/12/2021 Approved JACK KARGODORIAN
Drywall Nailing 11/18/2021 Approved JACK KARGODORIAN
Insulation 11/18/2021 Approved JACK KARGODORIAN
Gas Test 1/24/2022 Corrections Issued JACK KARGODORIAN
Gas Test 1/31/2022 Not Ready for Inspection JACK KARGODORIAN
Gas Test 2/8/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 2/14/2022 Corrections Issued JACK KARGODORIAN
Service/Power Release 2/14/2022 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 2/15/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 2/23/2022 Approved JACK KARGODORIAN
PLUMBING-Final 2/23/2022 Approved JACK KARGODORIAN
HVAC-Final 2/24/2022 Approved JACK KARGODORIAN
Final 3/11/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 3/11/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 3/11/2022 Approved JACK KARGODORIAN
Smoke Detectors 3/11/2022 Approved JACK KARGODORIAN
Final 3/25/2022 Corrections Issued DAVID MATSON
Final 3/31/2022 OK to Issue CofO JACK KARGODORIAN