17665 W MAYERLING ST 91344
Certificate Information: 17665 W MAYERLING ST 91344
- Application / Permit
- 20010-20000-02801
- Plan Check / Job No.
- B20VN10662
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (31'-0"x 26"-0") 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d) an (g). NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | TROY DEGUZMAN |
| Corrections Issued | 9/5/2020 | TROY DEGUZMAN |
| Quality Review Completed | 9/8/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/8/2020 | APPLICANT |
| Applicant returned to address corrections | 11/16/2020 | TROY DEGUZMAN |
| Plan Check Approved | 2/24/2021 | TROY DEGUZMAN |
| Issued | 2/24/2021 | APPLICANT |
| CofO in Progress | 3/3/2022 | DAVID SCANTLIN |
| Permit Finaled | 3/7/2022 | JOHN JANSON |
| CofO Issued | 3/7/2022 | JOHN JANSON |
| Permit Finaled | 3/7/2022 | JOHN JANSON |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/4/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 9/4/2020 | TROY DEGUZMAN |
| Address approval | Cleared | 11/10/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 11/12/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 11/18/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 2/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kaligi,, Sean; Lic. No.: M37797 | 655 N CENTRAL AVE 17TH FL GLENDALE, CA 91203 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/6/2021 | Partial Inspection | LILIANA PORTILLO |
| Pre-Inspection | 5/6/2021 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 5/6/2021 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 5/24/2021 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 5/24/2021 | Corrections Issued | MICHAEL PELHAM |
| Pre-Inspection | 5/24/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Sewer | 5/24/2021 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 5/24/2021 | Partial Approval | LILIANA PORTILLO |
| Special/Order Compliance | 5/24/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Sewer | 5/28/2021 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 5/28/2021 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/1/2021 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/6/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| METHANE-Barrier | 7/6/2021 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 7/6/2021 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 7/6/2021 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/8/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 7/8/2021 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/8/2021 | Approved | LILIANA PORTILLO |
| Special/Order Compliance | 7/8/2021 | Partial Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | LILIANA PORTILLO |
| Special/Order Compliance | 8/5/2021 | Partial Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 8/9/2021 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Wood Construction | 9/3/2021 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/7/2021 | Corrections Issued | LILIANA PORTILLO |
| Pre-Inspection | 9/7/2021 | Partial Inspection | ADAM ESCOTO |
| Wood Frame | 9/7/2021 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/15/2021 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/15/2021 | Approved | STEPHANIE SWANSON |
| Wood Frame | 9/15/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/24/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Wood Frame | 9/24/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 10/4/2021 | Approved | DAVID SCANTLIN |
| Insulation | 10/4/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/4/2021 | Partial Approval | DAVID SCANTLIN |
| METHANE-Rough | 10/4/2021 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 10/4/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 10/12/2021 | Approved | DAVID SCANTLIN |
| Shower Pan | 10/12/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/27/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 11/23/2021 | Approved | DAVID SCANTLIN |
| Final | 11/23/2021 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 11/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 11/23/2021 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 11/23/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 11/23/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 11/23/2021 | Approved | DAVID SCANTLIN |
| Green Building Final | 12/1/2021 | Approved | DAVID SCANTLIN |
| Final | 2/3/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Service/Power Release | 2/3/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/3/2022 | OK to Issue CofO | DAVID SCANTLIN |
| Service/Power Release | 3/3/2022 | Approved | DAVID SCANTLIN |