22827 W COHASSET ST 91307

Certificate Information: 22827 W COHASSET ST 91307

Application / Permit
20010-20000-02783
Plan Check / Job No.
B20VN10539
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' 1" X 20' 9" IRR.-SHAPE ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 2/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 8/19/2020 GURUNATH NESARAJAH
Corrections Issued 8/19/2020 GURUNATH NESARAJAH
Building Plans Picked Up 8/21/2020 APPLICANT
Plan Check Approved 1/13/2021 GURUNATH NESARAJAH
Issued 1/13/2021 APPLICANT
CofO in Progress 1/27/2023 CHRIS CHRISTENSEN
Permit Finaled 2/3/2023 JOHN JANSON
CofO Issued 2/3/2023 JOHN JANSON
Permit Finaled 2/3/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/3/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/3/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/8/2020 GABRIEL ROBLES
Sewer availability Cleared 9/8/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/13/2020 MATTHEW CRAIG
Construction near power lines Cleared 11/30/2020 RIDWAN HARDY

Contact Information

Architect Woodcraft,, Astra E; Lic. No.: C32722 20812 VENTURA BLVD SUITE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/15/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 3/15/2021 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 3/22/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 4/8/2021 Not Ready for Inspection DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 5/24/2021 Approved DAVID STEPANYAN
Sewer 6/9/2021 Approved DAVID STEPANYAN
Underground Mechanical 6/9/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 9/21/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 9/21/2021 Approved DAVID STEPANYAN
Green Building Rough 9/21/2021 Approved DAVID STEPANYAN
HVAC-Rough 9/21/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 10/1/2021 Approved DAVID STEPANYAN
HVAC-Rough 10/1/2021 Approved DAVID STEPANYAN
Insulation 10/1/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 10/13/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 10/19/2021 Approved DAVID STEPANYAN
Drywall Nailing 10/25/2021 Approved JESUS PINEDA
ELECTRICAL-Final 10/27/2022 Approved CHRIS CHRISTENSEN
Final 10/27/2022 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/27/2022 Approved CHRIS CHRISTENSEN
Green Building Final 10/27/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/27/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/27/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 10/27/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 10/27/2022 Approved CHRIS CHRISTENSEN
Final 1/26/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 1/26/2023 Approved CHRIS CHRISTENSEN