14735 W HESBY ST 91403
Certificate Information: 14735 W HESBY ST 91403
- Application / Permit
- 20010-20000-02781
- Plan Check / Job No.
- B20VN10533
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD W/ATT. GARAGE.
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | RODNEY SAMIIAN |
| Corrections Issued | 8/27/2020 | RODNEY SAMIIAN |
| Quality Review Completed | 8/27/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 8/27/2020 | APPLICANT |
| Applicant returned to address corrections | 10/20/2020 | RODNEY SAMIIAN |
| Applicant returned to address corrections | 12/2/2020 | RODNEY SAMIIAN |
| Plan Check Approved | 12/2/2020 | RODNEY SAMIIAN |
| Issued | 1/4/2021 | APPLICANT |
| CofO in Progress | 4/13/2022 | JACK KARGODORIAN |
| No Progress | 4/19/2022 | MATT KELLERMAN |
| CofO in Progress | 4/19/2022 | MATT KELLERMAN |
| CofO in Progress | 7/15/2022 | JACK KARGODORIAN |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
| CofO Issued | 8/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 9/1/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/1/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 9/24/2020 | KURT CORRAL |
| ZI | Cleared | 9/29/2020 | LAUREN PADICK |
| Low Impact Development | Cleared | 11/1/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/13/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Creative Home Remodeling Group Inc; Lic. No.: 943341-B | 11333 MOORPARK ST #214 STUDIO CITY, CA 91602 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2021 | Partial Approval | CHARLES POWELL |
| Sewer | 1/14/2021 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 1/15/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/22/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 1/22/2021 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 1/25/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 6/22/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/22/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Wood Frame | 6/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/25/2021 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 6/25/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/29/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 6/30/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 7/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 7/9/2021 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 1/10/2022 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/28/2022 | Approved | JACK KARGODORIAN |
| Final | 2/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 2/28/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 2/28/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 2/28/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 2/28/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 2/28/2022 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | JACK KARGODORIAN |
| Gas Test | 3/17/2022 | Conditional Approval | JACK KARGODORIAN |
| Final | 3/29/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Service/Power Release | 3/29/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 4/13/2022 | Corrections Issued | JACK KARGODORIAN |
| Service/Power Release | 4/13/2022 | Approved | JACK KARGODORIAN |
| Final | 4/21/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 7/15/2022 | OK to Issue CofO | JACK KARGODORIAN |