9936 W LULL ST 91504

Certificate Information: 9936 W LULL ST 91504

Application / Permit
20010-20000-02780
Plan Check / Job No.
B20VN10530
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 44'-10" X 26'-10" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 SELLA BENYAMIN
Corrections Issued 8/24/2020 SELLA BENYAMIN
Building Plans Picked Up 8/25/2020 APPLICANT
Plan Check Approved 7/1/2021 SELLA BENYAMIN
Issued 7/27/2021 APPLICANT
CofO in Progress 11/30/2022 DAVID ANDERSON
Permit Finaled 12/24/2022 MICHAEL SMITH
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 12/4/2020 RIDWAN HARDY
Low Impact Development Cleared 4/14/2021 SUNG JOON WON
Hydrant and Access approval Cleared 6/19/2021 ROBERT DUFF
Address approval Cleared 6/24/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/25/2021 CARLOS AGUILERA
Sewer availability Cleared 6/25/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/16/2021 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 11/30/2021 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 3/23/2022 Approved GREGG CUMMINGS
Green Building Rough 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 3/23/2022 Corrections Issued GREGG CUMMINGS
MERV13>=Rough 3/23/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 3/23/2022 Approved GREGG CUMMINGS
Verify Sprinkler Sign Off 3/23/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 3/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/8/2022 Approved MATTHEW NELSON
Green Building Rough 4/8/2022 Approved MATTHEW NELSON
HVAC-Rough 4/8/2022 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 4/8/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/18/2022 Approved WILLIAM WREN
Shower Pan 4/18/2022 Approved WILLIAM WREN
Insulation 4/21/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/21/2022 Approved MATTHEW NELSON
Underground Mechanical 4/21/2022 Partial Approval MATTHEW NELSON
Sewer 5/5/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/12/2022 Approved WILLIAM WREN
Final 11/14/2022 No Access for Inspection DAVID ANDERSON
Green Building Final 11/14/2022 Approved DAVID ANDERSON
MERV13>=Final 11/14/2022 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/14/2022 SGSOV Not Ready DAVID ANDERSON
Service/Power Release 11/14/2022 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 11/14/2022 Approved DAVID ANDERSON
Final 11/22/2022 OK to Issue CofO DAVID ANDERSON
MERV13>=Final 11/22/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved DAVID ANDERSON
Service/Power Release 11/22/2022 Approved DAVID ANDERSON