8006 N LONGRIDGE AVE 91605
Certificate Information: 8006 N LONGRIDGE AVE 91605
- Application / Permit
- 20010-20000-02779
- Plan Check / Job No.
- B20VN10528
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 23' X 61'-7" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | RAPHAEL ROSAS |
| Corrections Issued | 8/20/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 1/6/2021 | RAPHAEL ROSAS |
| Issued | 1/26/2021 | APPLICANT |
| CofO in Progress | 7/22/2022 | GREGG CUMMINGS |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
| CofO Issued | 8/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/8/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/24/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 12/10/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/28/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/30/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/13/2021 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 4/13/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/30/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/10/2021 | Partial Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/14/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/14/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/14/2021 | Approved | GREGG CUMMINGS |
| Wood Frame | 8/10/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/23/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/23/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 9/23/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 9/23/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/23/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/23/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 10/21/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 10/21/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 10/21/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 10/28/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/17/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/17/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/17/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/29/2021 | Partial Inspection | GREGG CUMMINGS |
| Gas Test | 3/10/2022 | Approved | GREGG CUMMINGS |
| Sewer | 3/10/2022 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 3/10/2022 | Approved | GREGG CUMMINGS |
| Sewer | 3/17/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 3/29/2022 | Approved | GREGG CUMMINGS |
| Final | 4/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 4/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 4/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 4/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 7/1/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 7/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 7/1/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| Final | 7/21/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/21/2022 | Approved | GREGG CUMMINGS |
| Service/Power Release | 7/21/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 7/21/2022 | Approved | GREGG CUMMINGS |